The pay application generator worked out one month at a time. Next month you had to rebuild the schedule of values yourself: add this period into previous, clear this period, and find last month's certified total for the "less previous certificates" line. If you skipped that last part, the page estimated it as previous work less retainage at today's rate, and said so. The estimate is wrong whenever the retainage rate has changed during the job.
It now has a Next month step. From a finished application it:
- sets each line's previous to previous plus this period;
- sets this period to zero;
- leaves stored materials in the stored column. On a continuation sheet, stored materials are kept apart from work until they are installed, so the page tells you which lines still carry stored materials and asks you to move them into this period once they are installed;
- keeps change orders as change orders, and keeps any line's own retainage rate;
- adds one to the application number and moves the period end a month (a period that ended on the last day of a month ends on the last day of the next one);
- sets previous certificates to this application's total earned less retainage (line 6). Previous certificates plus the payment due add up to that line, so once this application is paid in full, that is what has been certified. If the owner certified less, you type in the real figure.
You can start next month on the page straight away, or download the CSV and open it next month. Nothing is uploaded or saved by the page; the file is your record.
How it is checked
Three properties are tested in calc.test.mjs:
- A month rolled forward with no new work is due exactly $0.00. Taking the worked example, a renovation with a $532,300 contract sum to date after two change orders, the rolled application has $0.00 due and no "estimated" finding.
- $10,000 of new drywall billed on the rolled schedule at 10% retainage is due exactly $9,000.
- Three months chained (25%, then 20%, then 30% of a framing line, with stored roofing material) pay out, summed, exactly the third month's total earned less retainage. No cent goes missing between months.
What it does not do
It does not save jobs, track retainage until release, write lien waivers or handle several jobs at once. Those are the jobs of PayApps, our hosted pay-app billing for subcontractors (the earlier post has the competitor prices and the plan). PayApps opened on 2026-11-27: free on one active job, with no card, and it reads the generator's Excel download as a job's schedule of values and opening balance, so a job rolled forward here can carry on there (start free). Lien waivers, QuickBooks and job costing are in the paid plans, which are not on sale yet.
The page is not the AIA G702/G703 form and is not affiliated with the AIA. It does the arithmetic on your figures. Your contract decides the retainage terms, and it is not legal or accounting advice.