Save bids, mark them won or lost.
Keep this bid so it is still here when the customer calls back. Every number on this form is saved together, under a name you choose, along with the figure it gave you, and restoring one puts the whole job back exactly as you priced it. Mark each one won or lost when you hear — the ones you have not heard back on stay listed as waiting, with how long they have been out. Once a few have come back, this panel says how long yours actually take, and how many are still out past that. Once enough of them have been decided, it also says whether the bids you save here have been landing differently lately than they used to.
Kept in this browser only, on this site’s own storage. Nothing is uploaded, and clearing your browser data clears it — download a backup to keep a copy or open your bids on another device. Bids are kept per tool, so these are the ones you saved here.
Type the deck. You get joists, the beam, posts, footing concrete, deck board rows with joints on joists, a lumber order in stock lengths and a hardware count, from the same deck engine as the whole-house takeoff. Nothing leaves your browser.
Add a deck to a whole-house framing takeoff
For a 16 ft by 12 ft ledger-attached deck 36 in above grade with 2x8 joists at 16 in on center, the calculator counts 13 joists, a double 2x10 beam, 3 6x6 posts, 26 deck boards of 16 ft and 16 bags of concrete for the footings. Change any figure to match your deck.
Joists sit on every multiple of the spacing along the deck's width, plus one at the far end. At 16 in on center a 16 ft wide deck takes 13 joists. At 12 in it takes more and at 24 in fewer, but the decking you choose may need the closer spacing.
Boards run across the joists, so the number of rows is the deck's depth divided by a board's width plus its gap, rounded up. A 12 ft deep deck of 5-1/2 in boards with a 3/16 in gap is 26 rows. End joints are placed on a joist centre and staggered, and the last row may need ripping.
No. Joist, beam and post sizes are inputs you take from your local code's span tables or an engineer, and footing depth and diameter are typed figures because frost depth is local. The page counts lumber and hardware for the sizes you pick. A building department or licensed engineer decides what is allowed.
Checking a beam over three or more posts, or one running past a post? The free continuous beam calculator works out its moments, post reactions (including uplift) and deflection.