Whose delay is it? Splitting a P6 delay into owner, contractor and concurrent days

XER Schedule Check's time impact analysis now takes a Party column and splits the finish delay into each party's sole delay and the concurrent days.

Delay claims on construction jobs rarely come from one side. The owner issues a change while the contractor's crew is short; the city is slow with an inspection while a supplier ships late. Both sides then argue over the same days, and the question underneath is always the same: how much of the delay would have happened anyway, had one side caused nothing?

XER Schedule Check already ran a time impact analysis: write the delay events as a fragnet, insert them into the P6 update, and recompute. Today a fragnet row can name a Party. The tool then schedules each party's rows alone, and every row except that party's, and splits the finish delay three ways:

  • sole delay for each party: the total minus the run without it, the days that go away only if that party's events had not happened;
  • concurrent days: delay that stays whichever party's rows are taken out;
  • and the parts add up to the whole delay, by construction.

The worked example

On the built-in example, an invented office fit-out, the owner's change to the level 2 MEP layout adds 17 working days of redesign and re-approval, while the contractor's level 1 rough-in runs 20 working days long. Both feed the same in-wall inspection.

RunFinishWorking days later
As submitted2026-07-27
Owner's rows alone2026-07-303
Contractor's rows alone2026-08-068
Both2026-08-068

Take the owner's rows out and the finish still moves 8 days, so the owner's sole delay is 0. Take the contractor's out and it moves 3, so the contractor's sole delay is 5. The other 3 days stay either way: concurrent.

Adding up each event alone would have said 11 days of delay against a real 8, and nothing about whose days they are. The split answers the but-for question directly.

How it was checked

No public job publishes a fragnet with its parties, so fragnets were planted in six public P6 files (up to 16,000 activities), with answers that come from the logic and from plain one-activity runs, not from the split itself:

  • two driving activities in series, one per party: no concurrent days, each party's sole delay equal to its own delay, 19 of 19;
  • an owner lengthening an activity while the contractor adds a parallel copy with extra days of its own: total from the larger delay, concurrent from the smaller, 31 of 31;
  • one party only: it owns the whole delay, 30 of 30.

One thing the first run caught: four parallel plants measured a day more than the days added. Both parties' alone runs agreed, so the engine was consistent; the finish sat on work on another calendar, and a working day on that calendar is not one on the project calendar. The check now takes its expectations from plain runs instead of arithmetic. Details: ventures/xer-schedule-check/eval/tia-party-check-2026-11-23.md.

What it does not do

It splits the modelled delay by the schedule's logic. Whether concurrent days earn time, money, both or neither is set by the contract and the law that governs it. The guide, how to split concurrent delay between owner and contractor, walks through it. Everything runs in the browser; the schedule is never uploaded. Not legal, contractual or scheduling advice.