XER Schedule Check reads a Primavera P6 .xer export in the browser. Its recomputed dates match the ones P6 stored on 19,820 of 19,822 activities in six public files. As of today it also runs a time impact analysis, the method most contracts name for asking for (or granting) more time.
What a time impact analysis is
Something happens that the contractor did not plan for: the owner changes the mechanical layout, a permit is held, the door hardware approval comes back a month late. The contractor wants an extension of time. The usual way to show how much (AACE International Recommended Practice 52R-06) is:
- take the schedule update in force when the event happened;
- write the event as a fragnet: the new activities it added, how long each takes, what each follows and what each holds up;
- insert it, reschedule, and compare the finish with and without it.
Done by hand that is an afternoon in P6 per event, for someone who holds a P6 seat. Claims consultants charge by the hour for it. The owner's reviewer, who usually has the XER but not P6, has to take the result on trust.
What the tool does
The fragnet is a small table, pasted from a spreadsheet:
Activity ID,Name,Duration,Predecessors,Successors,Not before,Event
F100,Owner change notice: level 2 MEP layout,0,A1030,,2026-04-08,CO-03 MEP layout
F110,Redesign level 2 MEP rough-in,12,F100,F120,,CO-03 MEP layout
F120,Re-approve level 2 MEP drawings,5,F110,A1100,,CO-03 MEP layout
A1040,,+25,,,,Late hardware approval
Links read as A1030, A1030 SS or F110 FS+2 (lags in working days). +25 on an existing activity makes it 25 days longer. The rows go into a copy of the XER's tables the way a scheduler would type them into P6: a new activity on the calendar of the work it follows, the event date as a start-on-or-after constraint, lags on the project's lag calendar. The same engine then schedules the copy, and the page reports:
- how far the finish and every open milestone move, in working days of the project calendar;
- the float every other activity gives up, and which become critical;
- the driving path after the event, and whether the fragnet is on it;
- with two or more named events, each event alone. On the example office fit-out, the change order alone moves the finish 3 days and the late hardware 9, but together only 9: the change order's delay sits under the hardware's, which is what concurrency looks like in numbers.
It writes a printable exhibit for the request, a CSV, and the impacted XER itself, so the reviewer can import it into P6, press F9 and see the same dates.
How it was checked
No public job publishes its fragnets, so they were planted on the six public P6 files, each result against an answer reached another way (eval/tia-check-2026-11-20.md):
| Check | Agree |
|---|---|
| A zero-day fragnet between linked activities moves nothing | 120 / 120 |
| A new activity between A and its only successor = A made longer (finish, every milestone, the successor's start) | 115 / 115 |
| The impacted XER, written and read back, schedules to the same finish | 115 / 115 |
| An activity made d days longer moves the finish by d minus its float relative to the finish | 112 / 120 |
Of the 8 that did not, 7 run through activities on a calendar with different working days, where the delay crosses a non-work day the project calendar counts differently (a finish 7 days later for 6 added, 17.5 for 18.5), and the eighth is the expected-finish case below. The CCA hospital file has 16,000 activities and takes about 1.5 s per fragnet.
Where a delay hides
The planted checks found places where adding days to an activity moves nothing, all of them P6 behaving as designed:
- A milestone has no duration. P6 schedules it as an instant whatever the hours field says, so "+5 days" typed on a milestone vanishes. The tool now refuses it and says to insert a fragnet activity before the milestone.
- Expected finish dates absorb delay. With "use expected end dates" on, P6 shortens an activity's remaining duration so it still finishes on its expected date. On the public P6 24.12 file, 31 days added upstream of activity A10590 moved the finish by zero: A10590 started about six weeks later and finished on the same day. A time impact analysis on that schedule shows no delay unless someone notices. The tool now names every activity that did this, and a switch runs both schedules without expected finish dates.
- Start-to-start successors do not wait for the finish. On the public airport terminal file, three footing activities are linked to what follows only start-to-start. 39 days added to one of them moved the finish by zero, which is right: nothing after it waits for it to end. If the delay does hold the follow-on work up, the schedule is missing a link, and the tool says so.
- A finish-to-finish predecessor holds the finish. An activity whose finish is tied by an FF link starts earlier when made longer, so its finish does not move. The tool warns when a row does that.
The same run caught a plain bug: an activity ID ending in "-1" (A10390-1) was read as A10390 with a one-day lead, which closed a logic loop. An ID that the schedule or the fragnet holds is now taken whole.
Limits
It models the delay with the schedule's own logic. Who caused it, whether time is due under the contract, and how concurrent delay is apportioned are for the parties and their contract. It works on one update (a prospective or contemporaneous TIA); for what actually happened across a job's updates, the same tool's windows analysis is the retrospective method. Not legal, contractual or scheduling advice.