XER Schedule Check runs a time impact analysis (TIA) on a Primavera P6 .xer export in the browser: you write the delay event as a fragnet, the tool inserts it into the update and reschedules it with the file's own calendars and logic, and it tells you how far the finish moves. Today the fragnet can say that the event might go more than one way.
The problem with one path
A change order comes in. The designer redraws the level 2 MEP layout (12 days), and the drawings go back to the engineer. Most of the time they come back approved in 5 days. Sometimes they come back rejected, and the resubmittal takes 20.
A normal fragnet has to pick one. Pick the 5-day review and the request understates the risk; pick the 20-day one and the reviewer says you stacked the worst case. Paid schedule-risk products handle this with probabilistic branches. The tool's Monte Carlo risk run gained them this morning. The TIA did not have them until now.
How to write it
Add three columns to the fragnet, in any order:
Activity ID,Name,Duration,Predecessors,Successors,Branch group,Branch,Probability
F100,Owner change notice,0,A1030,,,,
F110,Redesign,12,F100,F120,,,
F120,Re-approve drawings,5,F110,A1100,Review,Pass,70%
F120,Re-approve after resubmittal,20,F110,A1100,Review,Resubmit,30%
A1040,,+25,,,Hardware,Late,40%
Rows that share a branch group are alternatives, and exactly one of them happens. Rows with no group happen every time. The same activity ID (F120 above) can appear on two branches with different durations. A branch whose probability is blank takes an equal share of what the others leave. If a group's probabilities add up to less than 100%, the rest goes to "none of these" (the hardware is on time 60% of the time). If they add up to more than 100%, the tool refuses the fragnet.
What comes out
A TIA has no random draws, so there is nothing to sample. The tool lists every combination of branches (up to 512) and schedules each one exactly the way it schedules a plain fragnet. On the example office fit-out above:
| Outcome | Probability | Delay (working days) |
|---|---|---|
| Review: Pass; Hardware: on time | 42% | 3 |
| Review: Pass; Hardware: Late | 28% | 9 |
| Review: Resubmit; Hardware: on time | 18% | 18 |
| Review: Resubmit; Hardware: Late | 12% | 18 |
The single most likely path says 3 days. The expected delay over all four outcomes is 9.2 days, with P50 at 9 and P80 at 18. A TIA that only took the most likely path would ask for about a third of the time the event is expected to cost.
The last row is worth a second look. When the resubmittal happens, late hardware adds nothing, because both delays land on the same finish and the longer one wins. That is concurrency, and the outcome table shows it without anyone having to argue for it. For each branch the tool also reports the expected delay if that branch happens. The gap between a group's branches (12.6 days for the review) is what that one decision is worth to the job.
The finish, milestones and float sections of the exhibit still describe one run, the most likely branch of each group, and they say so. The branches section sits above them in the page, the printable exhibit and the CSV.
How it was checked
eval/tia-branches-check.mjs plants two branch groups on each of the six public P6 files the tool is tested on. One group has two or three review durations under the same activity ID, sometimes with a rework activity that only one branch has. The other is a hold that may not happen. Every outcome's finish was compared with a plain TIA of exactly that outcome's rows, written out separately. The expectation was compared with the probability-weighted sum of those plain delays, and a single branch at 100% with the same rows written without branch columns. The counts are in eval/tia-branches-2026-11-22.md.
No public job publishes a fragnet with alternatives, so the branches were planted. The probabilities in a real request are a judgment the contractor has to defend, and the tool cannot supply them. It models the delay. Who caused it, and whether time is due, is a question for the contract. This is not legal, contractual or scheduling advice.