As-planned vs as-built from two P6 files, with a critical path nobody picked by eye

XER Schedule Check now lays a P6 baseline beside the as-built and splits the delay into steps along the as-built critical path that add up exactly.

Most construction delay claims open with the same exhibit: the plan beside what happened. AACE International's Recommended Practice 29R-03 calls it the observational, static method (MIP 3.1 for the whole job, 3.2 period by period). It is the cheapest method and the easiest to explain, and it is also where the arguments start, because someone has to say which chain of activities drove the actual finish, and that is usually picked by eye from a printout.

XER Schedule Check now does it from two .xer files in the browser: open the final update, then the baseline, and press Compare plan with as-built.

The path comes from the dates

The tool already builds an as-built model for its collapsed as-built analysis: a CPM schedule that lands every activity on its actual dates with the file's own logic (on the six public P6 files it is tested on, 21,404 of 21,422 activities). The as-built critical path is the chain of links in that model that leaves no slack into the actual finish. Nobody chooses it, and the page says how many activities the model put on their real dates, so a reader can see what the path rests on.

The delay, split into steps that add up

Walking that path from its first activity to the last, the gap between plan and record can only grow in two places: between an activity and the one that drove it (a late start) or inside an activity (it took longer). A negative step is time made up, or slack the plan had between two activities used up. Each step is a difference of variances, so they telescope: together with the float the plan gave the last activity on the path, they add up to the project's delay exactly. On the built-in example, an invented office fit-out 15 working days late:

ActivityStepWorking days
A1110 in-wall inspectionlate start: the city's date, three weeks after the plan's+14
A1180 furniture install (owner)late start+5
A1150 paintshorter duration-2
float the plan gave the last activity-2
sum, equal to the delay+15

Twenty of its 22 activities finished late, and door procurement ran 10 days long, but none of that is on the as-built critical path. Which of the many late activities to look at is the useful answer.

What had to be fixed before the numbers held

The check finishes each public file as planned with the tool's own status engine, with and without planted delays, so the right answer is known: built exactly to plan, all six files show no delay and no step; with 60 planted slips (1 to 3 activities, 1 to 30 working days), every step that grew the delay was on a slipped activity 59 times (the miss is a tenth of a day on the hotel file), and the steps added up to the delay 60 times of 60; of 60 planted waits, the 25 that landed on the as-built critical path each measured exactly their planted days. A second seed on five files: 50 of 50 and 50 of

  1. The first run was 57 of 60 and 58 of 60.

Four rules came out of the misses, each now in the code with the case that found it:

  • Calendars. Measured on the project calendar, a tight link between a six-day predecessor and a Sunday-to-Thursday milestone read as a day's late start, and a crew working 08:00 to 17:00 that started at 16:00 read as a longer duration. Steps are now measured on the activity's own calendar, and the remainder is shown as a separate calendar step.
  • Finish-to-finish links. An activity whose finish an FF link held is driven at its finish; the walk now takes that link over a tight SS link, and names the predecessor when an FF link explains a longer duration.
  • Ties. Of several tight links, the walk takes the predecessor that slipped most against the plan: the chain that pushed, not one that kept pace.
  • As late as possible. An ALAP activity is placed by its successor, so it never drives one, and no link into it is ever tight. The walk passes over ALAP predecessors, and through an ALAP activity follows the predecessor with least slack. On the hotel file, the plain driving-path walk stopped at an ALAP finish milestone after one activity; the tool now tries every activity finishing on the finish date and keeps the longest chain (79 activities).

Limits

It measures where the delay sits, not why, and not who is responsible. The planted delays were made by the tool itself, so this checks the method against a known answer, not against a consultant's exhibit on a real claim; a real baseline and final update, with the claim's own delay list, is the next test. Without a baseline file the final file's own Planned Start and Planned Finish stand in, which P6 resets whenever planned dates are reset, and the page says so.

There is a step-by-step guide: how to run an as-planned vs as-built schedule analysis.