P6's longest path rebuilt from the XER: 261 of 261 on five files, and a sixth whose flags contradict its float

XER Schedule Check now rebuilds P6's longest path, checks it against the flag P6 stores, and traces multiple float paths to any milestone, in the browser.

Every Primavera P6 .xer export carries a small piece of P6's own judgment: a driving_path_flag column on each activity, set to Y when that activity sat on the longest path at the last schedule run. A reviewer who receives the file without a P6 seat can't see that flag, and can't run P6's multiple float paths either. That's the analysis a delay consultant reaches for when the question is not "what drives the finish" but "what drives the roof being watertight by March".

XER Schedule Check now does both, in the browser, and checks the first one against P6's answer.

The longest path is a tree, not a chain

The tool's old driving path took one predecessor at each step. That's fine until two branches both drive the finish. In the airport terminal sample, 19 activities were on that single chain, while P6 had flagged 36. The other 17 sit on a second excavation-and-footings branch that finishes at the same moment.

The new longestPath() keeps every driving branch: every open activity from which a chain of zero-gap links reaches an activity finishing on the project finish. On the six public P6 files the CPM engine was already checked against:

FileP6 flaggedRebuiltOn both
Expressway (P6 7.0)333333
example (P6 24.12)171717
hotel (P6 6.0)133133133
sample (P6 20.12)424242
terminal (P6 5.0)363636
CCA (P6 6.0)6045656

Five files match exactly, with nothing extra. The sixth is the interesting one.

When the file disagrees with itself

On the CCA programme (14,270 open activities, heavily progressed) all 56 activities rebuilt here are flagged by P6, but P6 flags 548 more. Those 548 can't be on a longest path from the same run that wrote the file's dates. Some carry up to 3,788 hours of total float as P6 itself stored it, and that stored float agrees with the recomputed float on 14,268 of 14,270 activities. P6 also flags 399 activities that are already complete.

So the flags are almost certainly left over from an earlier run. Anyone who filters the file on that column is reading a stale critical path. The page and the command line now say so: they print how many activities P6 flagged, how many the logic gives, and the codes P6 flags that the logic doesn't.

Float paths to any activity

Total float tells you how far an activity can slip before the project finish moves. Ask about an interim milestone and it often can't answer. In the test suite, an activity feeding a milestone with a day to spare also feeds a long tail to the finish, so its total float is zero. To the milestone it has 8 hours.

floatPaths() computes float relative to the activity you name. It runs a backward pass from that activity alone, using the same link, lag-calendar and progress rules as the main engine, and measures each predecessor's float on its own calendar. Path 1 is the driving chain into the target. Each later path is the next-least-float chain among the activities not yet on one, the way P6's "free float" option ranks them. On the page, type an activity ID (or leave it blank for the finish), choose how many paths you want, and download the CSV.

There's no P6 answer to compare with: none of the six files stores P6's own float paths (float_path is empty in all of them). So the backward pass is checked by a property instead. Seeded at the finish's late date, it must never give an activity less float than its total float, and it must give the same float wherever the finish is what binds. Across 15,240 activities, no total float was above the bound. On the hotel file it matched on all 4,211. Getting there took two fixes, both visible in the counts. Summing link gaps across different calendars broke the property on 831 activities. Subtracting the SS lag of an activity that had already started (P6 treats that lag as spent) broke it on 143.

What's left

A public XER that stores P6's own float path numbers would let the path order be checked against P6 directly; ties between paths with equal float are ordered here by the later finish, which may not be P6's rule. The measurement is in the eval note.

This is a schedule-screening tool working on your own file, not scheduling, contractual or legal advice.