Where P6's resource tree goes in Microsoft Project: the resource Group, and back

461 of 502 resources in five public P6 files sit under a parent. The XER to Project converter now keeps that tree as each resource's Group, there and back.

P6 keeps its resources in a tree. A carpentry crew sits under "Trades", which sits under "Labour"; the dozer and the paver sit under "EQP". Planners group the resource sheet and the histograms by those branches, and a contractor's cost report often rolls up the same way.

Microsoft Project has no resource tree. So when the free XER to Project converter wrote a P6 schedule as Project XML, each resource came out flat, and the branches were gone. Going the other way, a Project file turned into an XER had no parents at all. Neither direction said so.

How common is the tree?

In the six public P6 files the tool is checked on, five have resources. 461 of their 502 resources have a parent, up to three levels deep. The Expressway file files 331 of 336 under 13 parents; the CCA file 117 of 119 under 14. None of those 33 parents is assigned to an activity. They exist to hold the tree. That is why they were dropped: by default the converter only writes resources the project's activities use.

The Group field

Project's resource sheet has a Group column. People use it for exactly this: grouping and filtering resources by trade or department. The converter now writes each resource's parents there as a path of P6 resource IDs, from the top down: EQP, or CCAD Project/LABOR MANHOURS. In Project you can group the resource sheet by Group, and the branches come back.

On the way back to an XER, each step of the path becomes a parent resource. When the file already holds a resource with that ID, it is used. When it does not, a labour resource of that ID is added. A plain Group such as "Electrical" from a Project file that never saw P6 becomes one parent named "Electrical", which is where a P6 user would file the electricians anyway.

What was checked

Through Project XML and back to an XER, every resource kept its parent path: 469 of 469 by default, and 502 of 502 with the "every resource" option. With the default, the 33 parents are rebuilt from the paths and named by their IDs, because an unassigned parent's full name is not in the XML. With "every resource" the parents are written as resources and keep their names. The XERs written passed the tool's P6 import checks, which now also look for a missing parent and a loop in the tree. In MPXJ's collection of Project test files, 14 of 14 work resources with a Group came back with the same Group.

What is not checked: an import into a real P6. Whether P6 matches a parent by resource ID to a resource already in its global dictionary, or adds a new one, is still open, as it is for every resource.

The measurements are in eval/resource-hierarchy-2026-11-22.md. The converter runs in your browser tab, and the XER is never uploaded.

All writing · More in Tools and projects · All tools and research