Carrying P6 resource curves into Microsoft Project, day by day

An XER converted to Project XML now keeps each P6 resource curve as timephased work: 33 of 33 on a public hospital schedule, read back by MPXJ.

XER Schedule Check turns a Primavera P6 XER into Microsoft Project XML, for the owner's rep or estimator who is sent a P6 schedule and works in Project. Until today the conversion wrote every resource assignment flat. A scheduler who had put an assignment on P6's Back Loaded curve, or on a contract's own curve, saw it spread evenly in Project: the resource usage view, the labour histogram and the S-curve all lost the shape.

Yesterday's post went the other way and found that Project's contours are not P6's curves of the same names. So a P6 curve can't simply become a Project contour number. Back Loaded in P6 is ten twentieths at 3.5% and ten at 6.5%. Project's back loaded is ten segments rising from 10% to 100% of peak units. A custom curve like the hospital file's "PCO119" has no Project counterpart at all.

What Project does keep

Project stores how it spreads every assignment, as rows of timephased work in the XML file (TimephasedData, type 1 for remaining work). An assignment whose rows were edited by hand is marked contour 8, "Contoured". That is a place to put any shape. The converter now writes, for each assignment on a curve that has not started:

  • rows from the activity's start to its finish, cut at every midnight and at the curve's twenty slice ends, so the work in each row falls at one rate;
  • each row's hours to the second, rounded on the running total, so the rows add up to the remaining hours exactly;
  • contour 8. Where the curve came from a Project contour on an earlier conversion, the contour's own number goes back instead, so a file sent Project to P6 to Project comes back as it left.

How it was checked

All files are public; the scripts and numbers are in the evaluation note.

  • A real P6 schedule. The public hospital file (P6 6.0, 36,808 assignments) has 36 on curves. 33 have hours left, and all 33 were written (23 on PCO119, 7 Back Loaded, one each on Triangular Increase, Front Loaded and Bell Shaped), with 70 to 567 rows each. Day by day they match the spread the tool's earned-value view uses to within 0.0003 hours, and they sum to the remaining hours exactly.
  • Project's own files, there and back. The 19 contoured assignments in the open-source MPXJ project's test files, saved by Project, went to XER and back. All 19 came back with their contour. Read at each of Project's own row ends, the cumulative work matched Project's to 0.037 hours, 15 of them exactly. Before today the trip came back flat, up to 31 hours off.
  • A second reader. MPXJ, an independent library most schedule converters build on, read every written file back. It found the same rows with work and the same hours on each row, and the contour that was written, 66 assignments out of 66.

What is still open

Nobody here has opened the rows in Microsoft Project itself. They follow the layout Project writes, and MPXJ reads them, but a Project open is the next check. Assignments already under way are still written flat, because how P6 re-fits a curve to the hours left is not in any public file. The rows carry work, so Project works out cost from rates, not from a curved cost.

The converter runs in the browser, so the schedule never leaves your machine: open an XER on the tool page and press Download for Microsoft Project (.xml), or run node cli.mjs file.xer --to-project file.xml.