P6 finish-date fields now survive a trip through Microsoft Project

XER Schedule Check now puts P6 finish-date UDFs in Project's Finish fields and reads Start and Finish fields back: 120 of 120 values, up from 0.

XER Schedule Check converts Primavera P6 .xer files to Microsoft Project XML and back, in the browser. Schedulers use P6 user-defined fields (UDFs) for things like access dates, permit expiry dates and "must be done by" dates for a trade. P6 has two kinds of date UDF, start dates and finish dates. Microsoft Project has three sets of custom date fields: Date1-10, Start1-10 and Finish1-10.

Until today the converter put both P6 kinds into Project's Date fields. The values went across, but a finish date came back to P6 as a start date. Going the other way was worse: anything a Project user kept in Start1-10 or Finish1-10 was dropped on the way to P6, with no warning.

What changed. Finish-date UDFs now go to Project's Finish1-10 fields (activity, WBS and resource). Start-date UDFs stay in Date1-10. On the way back, Start fields become start-date UDFs and Finish fields become finish-date UDFs.

How it was checked. The open-source MPXJ project publishes Project XML files saved by Microsoft Project 2003, 2007, 2010, 2013, 2016 and 2019, each with every Start and Finish field set on a task named after it. The field IDs Project wrote in those files match the ones the converter uses, all 20 of them. Through XML, to XER and back to XML:

beforenow
Project Start/Finish values carried to P6 with the right kind0 of 120120 of 120
...and back in a Project field of the same kind0 of 120120 of 120
A public P6 6.0 file's finish-date values back as finish dates0 of 182182 of 182

Nothing else in the round trip moved: same links, codes, schedule and UDF values on six public P6 files, and no P6 import problems.

What it does not do yet. Project has one Number type and P6 has integer and decimal. A decimal P6 field that holds only whole numbers still comes back as an integer field. The values are the same, but the type is not. And nothing here was opened in a real copy of P6 or Project: the checks use the files Project saved and MPXJ's reader.

The full measurement is in eval/finish-udfs-2026-11-22.md. The tool is free and MIT licensed. It is a schedule-checking aid, not professional scheduling or legal advice: check results against your own scheduling software before relying on them.