The monthly schedule narrative, drafted from two P6 updates, with the reasons left blank on purpose

XER Schedule Check now drafts the contractor's monthly schedule narrative from last month's and this month's XER, with every cause left as a fill-in.

XER Schedule Check has had an owner's-side comparison of two monthly P6 updates for a while: what changed, what to ask the contractor about, and how much of the slip came from progress and how much from revisions. Today it covers the other side of the same comparison: the contractor's monthly schedule narrative.

The chore

Most contracts that require a CPM schedule also require a written narrative with every update. USACE's UFGS 01 32 01.00 10 calls it the narrative report, and many state DOT and private specifications have their own version. The contents barely vary: status against the contract date, the critical path, work done, work planned and not done, every change made to the schedule and why, float, next month's work, delays and what is being done about them.

Most of that is lists the scheduler copies out of P6 layouts by hand each month. The lists are already in the two XER files.

What the draft fills in, and what it leaves

The tool now writes eight sections from last month's and this month's file. Every date, activity ID and day count comes from the files. Every cause and reason is left as a highlighted [FILL IN: ...].

That split is deliberate. A file can show that paint went from 10 days to 8 on the critical path. It cannot show why. A narrative is a contract document, and a plausible invented reason ("crew size increased") would be a false statement in it. So the tool fills in what the files can prove and leaves the rest for someone who was on the job. On the built-in example (two invented updates of an office fit-out) the draft leaves 20 fill-ins: one cause for each of the six activities that were due and didn't happen, one reason for each of nine changes, plus the slip, the critical-path sentence, an edited actual date, the delays and the recovery plan.

It also flags things a reviewer will reject before the update goes out: an actual date after the data date, or a reported actual that moved since last month.

How it was checked

There is no public series of real consecutive P6 updates, so the check builds one. Each of six public XER files is statused 20 working days forward as planned, then a slip goes on a driving activity due in that window and a lag goes on an unstarted driving link. In 18 runs, every planted slip showed up under "planned work not accomplished" and every planted lag under "changes", each with a fill-in. The draft never listed a change the comparison didn't find, and a file compared with itself produced no changes and no request for a recovery plan (eval/narrative-check-2026-11-22.md). On the 30 MB, 16,000-activity file the draft took about 4 seconds in Node.

What it does not show yet: whether a working scheduler finds the draft faster than their own template, or whether an owner's reviewer is happy with the section order. That needs a real user.

Try it

Open this month's XER on the tool page, then last month's in the comparison box, and scroll to "Contractor's monthly schedule narrative". Print it, or download it as HTML or plain text to paste into your letterhead. Both files stay in your browser. The guide goes through the sections one at a time.