P6 user-defined fields in Microsoft Project: 41,729 values a converter used to drop

XER Schedule Check now writes a P6 file's activity UDFs as named Number, Cost, Date and Text fields in Project XML, checked value by value with MPXJ.

XER Schedule Check converts a Primavera P6 .xer export to Microsoft Project XML in the browser, for the owner's rep, subcontractor or estimator who has Project and no P6 seat. Until today the conversion dropped every user-defined field (UDF) and only said how many it dropped.

That was the wrong thing to drop. On the largest public P6 file we test with, a 15,849-activity car park and hospital programme, the scheduler had added 32 activity UDFs and filled in 41,729 values: "Change Order #", "Claimed This Month", "July2011 Target % Complete", "NEW ACTIVITY ID", two access-date fields. That is the commercial record of the job, kept beside the logic. Someone opening the converted file in Project got the bars and lost the record.

What happens now

Each activity UDF becomes one of Project's spare custom fields, renamed to the UDF's title, so it shows up as a column you can group, filter and sort by:

  • integer and decimal UDFs go to Number1..20
  • cost UDFs go to Cost1..10
  • start and finish date UDFs go to Date1..10
  • text UDFs go to the Text fields that activity codes leave free

Indicator UDFs (P6's traffic lights) have no Project equivalent. They are listed in the conversion warnings with their counts, not dropped silently.

The field IDs were not typed from memory. They come from MPXJ's field table, and MPXJ is the open-source library most schedule converters are built on. We also asked it how a cost field is stored: in hundredths, so 1,234.56 is written as 123456.

Twenty-nine text columns, and who gets them

Project has 30 task text fields. Text1 holds the P6 activity ID, which leaves

  1. Activity codes already used them, one per code type. The CCA file has 37

code types and 15 text UDFs, so they cannot all fit.

The first rule we tried gave codes priority. On this file it would have dropped every text UDF, including a "change id" column filled on 15,548 activities, to keep code types filled on only 425. Now codes and text UDFs share the 29 fields, ranked by how many activities each fills, and a code type wins a tie. On CCA, 24 code types and 5 text UDFs get a field. 4,287 values do not fit (3,541 code assignments and 746 UDF values), against 29,971 under the codes-first rule. Each field left out is named in the warnings with its count.

How it was checked

We converted the six public P6 files and read every XML back two ways: with this tool's own Project XML reader, and with MPXJ 16.10. No public file has a cost UDF, so we also added a planted file with two cost fields (one with negative values), start and finish dates, an integer and a decimal: 124 values.

Values writtenRead back the same (our reader)MPXJ, same field and value
CCA (P6 6.0)40,98340,98340,983
Expressway (P6 7.0)1,8641,8641,864
Planted124124124

MPXJ also finds all 32 field names where they were meant to go. Nothing else in the conversion moved: 21,422 of 21,422 activities and 54,843 of 54,843 links still read back unchanged. The full method and limits are in eval/msproject-udfs-2026-11-21.md. The biggest limit: none of these files has been opened in Microsoft Project itself.

It works the other way too

The Project XML reader now turns Number, Cost and Date fields back into UDFs. So a Microsoft Project schedule that keeps its three-point estimates in Number fields called "Optimistic Duration" and "Pessimistic Duration" feeds the tool's Monte Carlo risk run the same way a P6 file's UDFs do. Before, that worked only for P6 files.

Try it with your own file at marisstella.app/xer-schedule-check. It runs in your browser and nothing is uploaded. The results are estimates from the file you give it, not professional scheduling advice.