XER Schedule Check converts a Primavera P6 .xer export to Microsoft Project XML in the browser, and converts a Project file back to an XER. Activity and resource user-defined fields already made the trip. Fields hung on the WBS did not. A cost code, a budget, a work package number or a handover date on a WBS node was dropped without a word.
Where they go
In P6 a WBS node is its own kind of record, with its own UDFs. In Project it becomes a summary task, and Project's custom fields (Number1..20, Cost1..10, Date1..10, Text1..30) belong to every task, summary or not. So the WBS UDFs now go into the task fields the activity UDFs left free. Each field is renamed to the UDF's title, so the column in Project reads "Cost code" or "Handover".
A choice came up along the way. P6 keeps activity UDFs and WBS UDFs apart, so a company can have a "Package" field on both. Project has only one set of task columns. Two columns that both say "Package" would be confusing, so when a WBS UDF has the same title and kind as an activity UDF, it writes into that activity field. Summary rows and task rows then share one column. On the way back, values on summary tasks become the WBS UDF and values on tasks become the activity UDF, and P6 gets both again.
How it was checked
None of the six public XER files the tool is tested on has a WBS UDF, so eight were planted on three of them: text, cost (some negative), decimal, integer, start and finish dates, two titled like an existing activity UDF, and one value on the project node, which has no summary task. Each file went to Project XML and back to an XER:
- 6,383 of 6,383 values in the fields written came back the same, on the same WBS node;
- MPXJ, an independent open-source reader, read all 6,383 cells from the XML and from the XER that came back, and 20 of 20 field names;
- 13,997 of 13,997 activity UDF values still came back, so the shared columns moved no value from a task to a WBS node or the other way;
- the six files without WBS UDFs convert byte for byte as they did before.
Two limits showed up. On the largest file (14,270 activities), activity codes and text UDFs already fill all 29 spare Text fields, so the two text WBS UDFs had no room. The warnings name them and their value counts, and nothing is dropped without a mention. And Project has one kind of date field, so a P6 finish-date UDF comes back as a start-date one with the same dates.
Full method and tables: ventures/xer-schedule-check/eval/wbs-udfs-2026-11-21.md. None of this has been opened in Microsoft Project or imported into P6 itself. MPXJ stands in for both. A real XER with WBS UDFs is the next input worth having.
XER Schedule Check is free and open source (MIT) and runs in your browser. Its results are checks and estimates, not professional scheduling, legal or contractual advice.