Schedulers put the reasons behind dates in Primavera P6's activity notebook: "Submitted as clause 14", "Rain 12-14 March", "client to confirm finishes". When the schedule goes to someone who works in Microsoft Project, those notes should go with it. Until this morning, XER Schedule Check dropped them. It counted them ("not carried: 87 notebook entries") in both directions, P6 to Project and Project to P6.
Two different shapes
P6 keeps one entry per notebook topic. Topics are a list the database defines (Description, Delays, Anticipated Problems...), and an activity can have an entry under several. Each entry is HTML from P6's editor. P6 desktop writes a full <HTML><HEAD>... document with each line break stored in the XER as two 0x7F bytes. P6 Web writes <HTML><BODY><P>...</P></BODY></HTML>. Some files hold plain text.
Microsoft Project has one plain-text Notes field per task.
So the converter now writes a task's notebook into its notes, topic by topic in P6's topic order, each under its topic's name in brackets:
[Description]
Pour after the cube results.
[Delays]
Rain 12-14 March.
WBS notebooks go on the summary tasks, and the project node's on the project summary task. Going the other way, a note in that form becomes one notebook entry per topic. Any other note, the kind a Project planner types, becomes one entry under a topic called "Notes". A schedule can go P6 to Project to P6 and keep its notebook.
Two details needed care. A line inside a note that looks like a heading ([see RFI 12] after a blank line) is written indented one space, so it stays in its entry. The topic order is rebuilt from the order in every note, because P6 lists topics by a sequence number that Project has nowhere to keep.
How we checked it
The six public P6 files we test against hold 88 real notebook entries. Most are one-word tags on a 2013 expressway schedule; there is also a DHTML clause reference and one P6 Web note. All 88 appear in the Project XML under their topic. All 88 come back to the XER on the same activity, under the same topic, with the same text.
Eighty-eight short entries is not much, so we planted 2,006 more across the six files. They come in desktop, Web and plain-text form, with lists, line breaks, entities, quotes, accents and lines that look like headings. The generator also wrote the text a person should see. All 2,006 read as meant and came back unchanged. 700 of 700 activities with several topics kept their order, and P6's import rules found nothing to refuse.
We also checked against MPXJ, the open-source library most schedule converters use. It read the same words from the original XER and from ours on 1,702 of 1,713 entries. The other 11 are a project-level entry MPXJ shows on no task in either file, and 9 planted plain-text entries that start with a quote mark, which MPXJ misreads in the original.
A bug found on the way
To compare with MPXJ we had to save the XER files. MPXJ read "façade" in our Project-to-P6 output as "façade". The converter saved UTF-8, while P6 writes an XER in the Windows code page and readers such as MPXJ expect one. That hit every accented task name, not only notes. The file is now saved in Windows-1252. When a character does not fit (a Cyrillic name, say), it stays UTF-8 and the tool says so.
What it does not do
The text goes across, not the formatting: bold, colour and tables are lost, because Project's XML notes are plain text. We have neither a P6 nor a Project seat, so the files have not been opened in either program. The checks use two independent readers (this tool's own and MPXJ) and the field lists of real P6 exports. Details and every number: eval/notebooks-2026-11-21.md.
The converter runs in the browser tab; the file is not uploaded. It is not professional advice. Have a scheduler check anything you submit.