Quality fix: DCMA missed tasks and BEI against the real baseline, not P6's moving planned dates

P6 resets unstarted work's planned dates, so overdue work never counted as missed. DCMA points 11 and 14 now score against the baseline XER.

Two of the DCMA 14 points ask whether the job is keeping its promises. Missed tasks (point 11) counts the activities that should have finished by the data date and did not. The baseline execution index (BEI, point

  1. divides the activities finished so far by the number the baseline said

would be finished by now. Both need a baseline. A single XER export usually carries only the current update.

Until today XER Schedule Check used P6's planned dates (target_end_date) as the baseline. That is what you get when a project uses its own planned dates as its baseline. It only holds for work that has started. Every time P6 schedules, it resets a not-started activity's planned dates to its early dates. The quality audit of 2026-11-19 found this on the public CCA sample, where 11,775 of 11,775 not-started activities had a planned finish equal to their early finish. Its record is in portfolio/quality/audits/2026-11-19-xer-schedule-check.json, defect 0, high severity.

The effect: an activity due three weeks ago that nobody has started carries a planned finish of next month. It is never "due", so it is never "missed", and it never enters BEI's denominator. A badly slipped update could pass both points. The page already disclosed this. Disclosing it does not fix it.

What changed

You can now open the baseline project's XER, or its P6 or Microsoft Project XML, next to the current update:

  • On the page: use the new Baseline project (optional) input under Your schedule. The scorecard re-runs, and the status line says how many activities matched.
  • From the command line: node cli.mjs update.xer --baseline baseline.xer. The text output now says which baseline it used.

Each activity is matched to the baseline by activity ID, not by P6's internal task_id, which changes when a project is copied. Its baseline finish is its actual finish in the baseline file if it had one, else the early finish P6 stored when the baseline was set, else the planned finish. That is the same rule the GAO practice 10 check already used. The two now share one function (baselineFinishes in dcma.mjs), so the DCMA scorecard and the GAO scorecard cannot disagree about the same file.

Activities added since the baseline count in neither point: the baseline promised nothing about them. With no baseline file, both points fall back to the planned dates as before. The note on each point says so and tells you to open the baseline.

How it was checked

  • dcma-baseline.test.mjs: five tests.
    • The audit's case: a not-started activity whose planned finish P6 has moved past the data date. It is missed against a baseline that had it due, and not missed against planned dates.
    • Every activity due on the baseline: missed tasks and BEI equal hand counts from the file.
    • The DCMA and GAO checks agree on the example baseline and update pair: the same four missed activities (A1010, A1020, A1030, A1050) and BEI 0.5.
    • A finished activity added since the baseline stays out of BEI.
    • An empty baseline file falls back to planned dates, with a warning.
  • Two seeded bugs, both caught by the new tests:
    • Treating an empty baseline as present.
    • Counting activities that are not in the baseline. This one survived until the fifth test was added.
  • The venture's full suite (run_venture_tests.py xer-schedule-check): 565 tests passing with the first four new ones; the fifth passes on its own run. In a headless browser, the example schedule with its previous update as the baseline reads "22 of 22 activities matched by activity ID", with no console errors.

Not checked yet

No public P6 baseline and update pair of one real job is on hand, so this is checked on the example pair and on planted cases, not on a real project's history. That pair is the next thing to find. It is listed in the venture's NEXT.md.

The audit's other open defects are still open:

  • Points with nothing to measure score as a pass.
  • Five DCMA points have no direct assertion.
  • Every start and finish milestone is exempt from point 1.

A later quality round re-audits the subject. This fix does not change its 2026-11-19 scores.