A DCMA 14-point check on a whole schedule ends with a sentence like "17.6% of relationships carry a lag". True, and nobody owns it. The owner's rep sends it to the general contractor, who has to work out whose fragnets hold the lags before anything gets fixed. Commercial schedule-analysis seats answer this with a "ribbon" view: the same metrics broken down by WBS or activity code, one row per area or subcontractor.
XER Schedule Check does that now, free and in the browser. Open a P6 XER (or P6 XML, or Microsoft Project XML), pick WBS or any activity code the scheduler set up, and press Break down the 14 points. Each group gets points 1 to 11 scored on its own activities against the same DCMA thresholds, worst first, with a CSV to send each party its row (node cli.mjs schedule.xer --ribbon Responsibility from the command line). A relationship counts under its successor, since the successor's scheduler owns the link into their work. The critical path test, CPLI and BEI describe the whole network, so they stay project-wide.
What it shows on real files
On a public hotel schedule (4,217 open activities) grouped by its Responsibility code, the project fails 5 points, but not the same 5 for everyone:
| Responsibility | Open | Lags | High duration | No resource |
|---|---|---|---|---|
| Aluminium subcontractor | 60 | 35.9% | 21.8% | 100% |
| Main contractor | 2,311 | 17.7% | 0.3% | 97.6% |
| MEP subcontractor | 1,404 | 20.4% | 1.2% | 5.1% |
| Steel structure subcontractor | 91 | 7.1% | 5.5% | 100% |
The MEP subcontractor resource-loaded its work; the main contractor did not. The aluminium subcontractor's 60 activities hold the most lags and the most long activities. Three different letters.
On the public CCA hospital file (14,270 open activities) by division, Fire Protection and Telecom and Security have 92.7% and 98.3% of their open activities on negative float. Across the whole file it is 3.8% (544 activities), because 12,845 open activities carry no division and almost none of them is on negative float. The project-wide point hides the two trades that are behind.
How it was checked
eval/ribbon-check.mjs runs every WBS level from 1 to 3 and every flat activity code type on the six public P6 files the tool is tested on: 58 groupings. In every one, each point's group counts add up to the project-wide count, every group's pass flag matches its count against the threshold, and all 34,287 findings land in the same group when assigned a second way, by their activity ID text looked up in the file's own WBS and code tables rather than through the ids the module uses. The details are in ventures/xer-schedule-check/eval/ribbon-check-2026-11-24.md, and a guide walks through it.
Two cautions. Small groups swing: one activity in a group of three is 33%, so read the count beside the percentage. And the breakdown is only as good as the coding; on the hospital file most of the work has no division at all, which is itself worth a comment to the scheduler.
The DCMA points are screening metrics, not a verdict on a schedule, and none of this is scheduling, contractual or legal advice. The tool is not affiliated with Oracle or the DCMA.