Re-audit: the XER checker now scores BEI against a real baseline, and its tests still miss three seeded bugs

A re-check of XER Schedule Check against its 2026-11-19 audit. The baseline gap is closed and five of nine defects are fixed; verification still misses the bar.

XER Schedule Check runs the DCMA 14-point assessment on a Primavera P6 XER file in the browser, without a P6 seat. The 2026-11-19 audit found nine defects. The worst was in points 11 (missed tasks) and 14 (BEI): it measured them against P6's planned dates. P6 resets those dates to the early dates for every activity that hasn't started, each time it schedules. So late work that never started was never counted as due or missed: 0 of 11,775 on the public CCA file. This re-check tested all nine defects against the code on main today. The full record is in the re-audit file.

Verdict: still below the bar, now only on verification. Correctness, claims and domain score 3. Verification scores 2.

Why planned dates are not a baseline

If you review contractor updates, this matters outside this tool too. DCMA's BEI is activities finished to date / activities the baseline had due by the data date. A P6 update without its baseline has only planned dates (target_end_date), and P6 moves them for unstarted work. An update can be weeks behind and still score BEI 1.0 on planned dates. You need the baseline XER. The tool now takes one: open it next to the update on the page, or pass --baseline on the command line. Activities are matched by activity ID.

To check that, we built a baseline from the CCA file in which every unstarted activity was due before the data date, then counted DCMA 11 and 14 with our own script. Both gave the same result: 13,228 due, 11,694 missed (88.4%), BEI 0.116. On planned dates the same file reads 2,316 due and BEI 0.662.

What the fixes closed

earlier defecton arrival
missed tasks and BEI on planned dates, no way to load a baseline (high)closed: baseline file on the page and CLI; matches an independent count
FAQ said planned dates equal the baseline (medium)closed
README credited unit tests that did not exist (medium)closed (the replacement line understated one test; corrected here)
CLI stack traces on bad input (low)closed, though the earlier audit had not marked it
CLI rounded BEI to one decimal (low)closed
points with nothing to measure scored PASS (medium)open
7 of 9 seeded bugs survived the tests (medium)open on arrival; this round's tests catch 4 of the 7
every start/finish milestone exempt from point 1 (low)open
LOE and WBS-summary predecessors counted in points 2-4 (low)open

What we recomputed

  • DCMA points 1-8 on four public XERs (Expressway, CCA, hotel, terminal) with our own Python counter: 40 of 40 counts identical.
  • CPLI on a hand case: 20 working days of critical path, must-finish date 5 days early, so (20 - 5) / 20 = 0.75. The tool gives the same.
  • The tool's own schedule calculation against P6's stored dates on CCA: 14,268 of 14,270 open activities agree.
  • The page in Chromium at phone width, on the 30 MB CCA file with the baseline: scorecard in 2.4 s, no requests leave the page.

What is still not at the bar

  • The headline pass count includes points that had nothing to measure. On Expressway, "8 of 14 pass" counts missed tasks (0 of 0), BEI (n/a) and CPLI (set to 1 because there is no must-finish date). A scheduler should read three of those eight as n/a.
  • Seeded bugs still survive. On arrival the same seven of nine survived as on 2026-11-19. New tests in dcma-thresholds.test.mjs test each threshold just above and just below its line for points 6, 7, 13 and 14, and those four bugs now fail a test. Three still pass every test: point 12's 600-day margin cut to 300, the start-to-finish backward lag dropped, and the start-float branch swapped.
  • Point 1 exempts every milestone, not just the project's start and finish. Points 2-4 count 698 links out of LOE or WBS-summary activities on CCA, which takes the FS share from 85.0% to 84.0%.

The open items are listed in the product's NEXT.md. Each changes a published score across the page, CLI, written report, ribbon and trend views, so each needs its own change.

Screening metrics, not a verdict on a schedule. Not affiliated with Oracle or the DCMA.