XER Schedule Check recomputes a Primavera P6 schedule in the browser and checks its dates against the ones P6 stored in the same file. This morning it matched early finish, late finish and total float on 19,808 of 19,822 open activities in six public XER files. All 14 misses were in one file: a 14,270-activity programme saved by P6 6.0 with a data date of 30 September 2011 and 2,134 out-of-sequence links.
Five more rules take it to 19,820 of 19,822. Late finish now matches on all 19,822. The other five files did not change. Each rule came from one mismatch, and we kept a rule only if the total went up. Each one can be switched off to repeat the run without it (method and every count).
1. A lag into a finished activity comes back off
Earlier we found that a finished activity takes no lag back from its successors. Turning the link around gives a different result. When an open activity feeds a finished one with an FS lag of 120 hours, the forward pass pushes the finished node to the open activity's finish plus 120 hours. P6 mirrors that going back: the open activity's late finish was exactly 120 hours of work before the node's late date. That fixed a chain of five activities that P6 had 20 days earlier than we did. Doing the same for SS and FF links lost 31 matches, so the rule is FS only.
2. A labour row's leftover hours set the late start
Two started activities had no remaining duration, yet P6 stored a late start weeks before their late finish: 448.8 hours on one, 239 on the other. The number is in the resource assignments. Each has a labour row whose remaining work runs from restart_date to reend_date, and that span is exactly 448.8 and 239 working hours. P6 rolls the assignment's late dates up to the activity, so in the backward pass the activity behaves as if that work were left. Its early dates still use a duration of zero. This fixed three activities, including one whose late finish P6 had 36 days later than we did.
3. Unspent SS lag counts going back as well
Take a start-to-start lag of 96 hours from an activity that started 28 working hours before the data date. The successor still waits for the other 68 hours, counted from where the remaining work starts. We already did this going forward. Going back, P6 does the same when the successor is a finished node: the predecessor's late start is 68 hours before the node's late date.
4. As late as possible also applies to started work
An activity with an as-late-as-possible constraint and 9.6 hours left had its remaining work moved up against its successor's start. We had applied that constraint only to activities that had not started. The actual start stays where it was.
5. An actual start after the data date has spent no lag
One activity in the file records an actual start in August 2012, almost a year after the data date, which is a data error that P6 accepts. Its successors behaved as if none of their 96-hour SS lag had run. Treating every started predecessor this way lost 9 matches, so the rule covers only an actual start later than the data date.
The two left
A finish milestone and its successor still differ. P6 puts the milestone 24 days earlier than we do. Its predecessor is a finished milestone with a 608-hour FS lag from an actual finish on 31 July 2011. On the predecessor's calendar that lands on 29 October. P6 stored 5 October, which is 440 working hours after the actual finish or 32 after the data date. We tried the target finish, the data date, the 7-day calendar and a 24-hour clock, and none of them comes to 608 hours. We are leaving it as an open question rather than adding a rule that fits one activity.
Six files from six sources is still a small sample, and a seventh exporter could show a rule none of these does. If you have a progressed XER you can share, run it through the tool. The check runs entirely in your browser.