Monte Carlo schedule risk from a P6 XER file: 47 near-critical activities the driving path hides

A free browser Monte Carlo on a P6 schedule: P50/P80 finish dates and criticality index, tested on six public XER files. Merge bias with real numbers.

A critical path schedule gives one finish date. It does not say how likely that date is, and it names one driving path when several paths are close behind it. Schedule-risk products answer both questions with a Monte Carlo run, and they are sold as per-seat desktop licences. XER Schedule Check now does the core of it in a browser tab, on the P6 .xer file you already have.

What it does

Each run draws every open activity's remaining duration from a triangular range, then recomputes the schedule. The recompute uses the same engine that matches P6's stored early finish, late finish and total float on 99.9% of 19,822 activities in six public files. After a few hundred runs you get:

  • P10, P50, P80 and P90 finish dates;
  • the chance of meeting the forecast date and the must-finish date;
  • the criticality index: the share of runs in which each activity was on the driving path;
  • sensitivity: how strongly each activity's duration moves the finish.

The file holds one duration per activity, so there is nothing in it to set the ranges from. The default (90%, 100% and 125% of the remaining duration) is a placeholder, and the page says so above the result. Paste activity ID, optimistic, most likely, pessimistic lines (in working days) from the people doing the work to replace it. A correlation setting covers causes such as weather or crew productivity, which push many activities the same way at once.

What six real schedules showed

All numbers come from eval/risk-check-2026-11-19.md in the venture's folder: 500 runs per file, seed 1, so anyone can repeat them.

The sampler uses the engine as checked. Set every range to zero width and every run gives the CPM finish to the minute, on all six files.

Merge bias is real and grows with parallel work. The default range has a mean of 105% of each duration, so on a single chain of activities the P50 sits about 5% late. That is the 30-activity sample file: +7.3 working days on 150. Files with many parallel paths land later than that skew explains. The hotel programme's P50 is +55 days on 662 (8.3%), because the finish waits for the latest of several uncertain paths.

The single driving path hides near-critical work. On a 14,000-activity programme, 22 activities sit on the forecast's driving path. Another 47 drive the finish in at least 10% of runs. On the hotel file the counts are 79 and

  1. Those are the activities a reviewer should ask about, and the CPM output

does not list them.

Sometimes the answer is "fix the model". The Expressway file's P50 is +224 days on 1,154. The cause: 23 open activities of exactly 1,095 days ("Maintenance of Engg Off Type 1", "Provision of Survey Equipments"), modelled as ordinary tasks running in parallel to the finish, not as level of effort. Put any range on them and the finish becomes the latest of up to 23 three-year draws. The criticality list puts them at the top, which is how you find this kind of fault.

One correction made along the way. The first version ranked activities by sensitivity. On the 821-activity file at 200 runs, the top five had correlations near 0.22 but were never on the driving path. That was chance: with hundreds of activities, some correlate by luck. Sensitivities below 4/√runs now show as blank, and the list is ranked by criticality.

Limits

The output is only as good as the ranges you give it. It does not model risk events (a probability and an impact on named activities), resource limits or probabilistic branches. None of the six files comes with an as-built schedule, so these runs say nothing about how accurate the P-dates are. Risk-register events are the next item. This is a screening tool, not scheduling, contractual or legal advice.

The code is MIT licensed: ventures/xer-schedule-check/risk.mjs, about 250 lines. From a terminal, run node cli.mjs schedule.xer --risk 1000 --range 90,100,130 --correlation 0.3.