The near-critical work a float filter misses: Monte Carlo risk in a P6 schedule review

On a 14,270-activity P6 programme, the 18 activities that drive the finish in a quarter of Monte Carlo runs all have 15+ days of float.

XER Schedule Check already wrote a review an owner's rep can send a contractor: the DCMA 14-point faults, ranked, with the exact activities behind each. It also ran a Monte Carlo finish-date risk analysis. The two did not meet. Now they do: run the risk analysis on the page, and the printed review carries a Finish date risk section (the ranges assumed, P10 to P90 with and without the risk register, the chance of the forecast and must-finish dates, the events ranked) and three corrections a risk run can back.

The three asks

  • Must-finish date met in under half the runs (high; under 80% medium): show the recovery or the time extension. The review says whether the forecast itself already misses the date or only the uncertainty does.
  • Near-critical activities: off the forecast's driving path, but driving the finish in a quarter or more of runs (medium). Manage them as critical.
  • No stated contingency when the forecast is met in under half the runs (low).

What it found on six real files

On six public P6 exports (P6 5.0 to 24.12), using the default range of 90 / 100 / 125% of remaining duration:

  • The near-critical list was identical between two random seeds on every file that had one, so it is not sampling noise.
  • On the largest file, a 14,270-activity programme, the risk run flags 18 activities with 15.7 to 18.7 working days of total float. A reviewer's usual "float under 10 days" filter lists 746 activities on that file and none of these 18. Their paths are long enough that a 25% tail on every duration lets them overtake the forecast's driving path in a quarter of runs.
  • On a 4,217-activity hotel schedule, 617 activities have under 10 days of float; the risk run picks out 8 zero-float activities that sit off the single driving path.
  • Every file with a must-finish date failed the must-finish ask (0 to 3.3% of runs on time), because the date sits 0 to 10 days after the forecast. That is often how P6 projects are set up, which is worth knowing before reading too much into it.

The ranges are the weak point: an XER file stores one duration per activity, so the default is an assumption, and the review prints it as one. Paste ranges from the people doing the work, or a risk register, and the same section uses those.

Method and numbers: ventures/xer-schedule-check/eval/review-risk-check-2026-11-19.md. Command line: node cli.mjs schedule.xer --risk 500 --report review.html.

Screening output from the file alone, not scheduling or contractual advice.