When a job is late, someone asks what it would take to win the time back. The schedule shows a critical path, and every activity on it has the same total float, usually zero. Float says these activities matter. It doesn't say which one is worth paying overtime on.
XER Schedule Check now answers that with critical path drag. Stephen Devaux defined it in Total Project Control (1999): an activity's drag is how much earlier the project would finish if that activity took no time, with everything else left as it is. It is the most that speeding up that one activity can ever win. Neither Primavera P6 nor Microsoft Project computes it.
How it is worked out
You can do it by hand in P6. Set one critical activity's remaining duration to zero, reschedule, write down the new finish, undo, and repeat for every activity. The tool does exactly that, in the browser, using the same scheduling engine as the rest of the tool. That engine handles calendars, lag calendars, SS/FF/SF links, constraints, progress and retained logic. It runs once for each activity on the longest path and once for each lag between them. Type a cost per calendar day of finish (liquidated damages, extended site overheads) and each row also gets a drag cost.
Rescheduling also catches two things a float formula can miss:
- Reverse drag. The critical path can enter an activity at its finish (a finish-to-finish link) and leave from its start (a start-to-start link). Shortening that activity moves its start later, so the project finishes later. The tool flags these rows.
- Stepped gains. On real calendars, shortening an activity by its drag doesn't always win the whole drag. The tool reports the smallest shortening that does.
What six public schedules show
I ran it on the six public P6 files the tool is tested against (eval/drag-check-2026-11-22.md in the repository):
| File | Longest-path activities | With drag |
|---|---|---|
| CCA (19,822 activities) | 54 | 4 |
| Expressway | 31 | 1 |
| Demo file | 13 | 12 |
| Hotel | 130 | 2 |
| Wind farm sample | 30 | 30 |
| Airport terminal | 33 | 1 |
In four of the six files, almost nothing on the critical path has any drag. The airport terminal has 33 activities on the longest path, but parallel chains of the same length run alongside them. Shorten any one of those activities and the chain next to it still sets the finish. Only one activity, an excavation, holds the finish back, and only by a day. If a manager picked the longest critical activity and added a second crew, the finish would not move at all.
Reverse drag shows up in real files too. Two activities in the hotel schedule are linked FF+600 h in and SS+408 h out. Take either one to zero duration and the finish moves 111 or 117 working days later. That says more about the logic than about the work, and it's the kind of link a reviewer should ask about.
On the CCA file, one bracket activity on level 12 (T12CO04403C0) has 14.7 hours of drag. Shortening it by 14.7 hours wins only 8 hours. It takes 22.8 hours of shortening to win all 14.7, because its finish-to-finish successor lands on day boundaries.
How it was checked
To check the tool, I built 200 random networks (2,477 activities) and computed the right answer with a ten-line longest-path calculation that shares no code with the scheduling engine. The tool's drag matched it on all 2,477. On the six real files, shortening each activity by exactly its drag moved the finish by exactly that much for 47 of 50 activities. The three exceptions each have a known cause: an expected finish date that overrides any shorter duration, an activity on a different calendar from the project, and the stepped gain above. The tool says which applies on each row. No commercial drag calculation has been compared yet, because none is public for these files.
There's a step-by-step guide to finding critical path drag in a P6 schedule, and the command line is node cli.mjs schedule.xer --drag --drag-cost 12500. Your file is read and rescheduled in your browser tab and never uploaded.