P6 expected finish dates: the setting that lets an activity swallow a slip

With 'use expected end dates' on, P6 shortens an activity to hit a typed date, so upstream delay vanishes. XER Schedule Check now models it and lists each one.

Primavera P6 has a schedule option called use expected end dates. Turn it on, type an expected finish on an activity, and P6 stops treating that activity's remaining duration as an estimate. Each time it schedules, it sets the remaining duration to whatever working time is left between the start of the remaining work and the date you typed. If a predecessor runs two weeks late, the activity gets two weeks shorter and finishes on the same day. Nothing after it moves.

Sometimes that is right: a crew really will finish on a fixed date. But in a schedule update a contractor sends an owner, it is also an easy way to hide delay. The DCMA 14 points don't look for it, and the dates P6 stores look normal.

What changed in XER Schedule Check

XER Schedule Check recomputes a P6 schedule from its logic in the browser. Until today it ignored expected finishes. On an unchanged file that made no difference, because P6 has already written the shortened durations into the file. In any what-if, though, the engine was wrong: the critical path test, last month against this month, the half-step split, the risk run and levelling. Now:

  • When a project has the option on, the engine does what P6 does. The remaining duration runs from where the remaining work starts to the expected finish. If the expected finish is at or before that start, it is ignored and the stored duration stands.
  • A new finding, Expected finish dates setting durations, lists every such activity. For each one it gives the duration the date set against the original duration. If the file records percent complete, it also gives the time left at the rate the work has gone so far. Dates that have already passed are listed separately, to be cleared. The written review ranks the finding medium, as logic that can hide delay.

Checked on a real file

Of the six public XER files used to check the engine, one P6 24.12 export stores expected finishes, on 23 open activities. The full write-up is eval/expected-finish-2026-11-19.md:

  • On 21 of the 23, the expected finish is after the remaining start. On all 21, P6's stored remaining duration is exactly the working time to the expected finish.
  • The other 2 have expected finishes from before the data date. P6 ignored them and kept their durations, and the engine does the same.
  • We then added 80 hours to each of the 21 stored durations. With the rule on, the engine still reproduced P6's early finish, late finish and total float on 404 of 404 open activities. With it off: 0 of 404.
  • Delaying each activity's latest-finishing predecessor by 10 working days moved two of them 0 days instead of 10. One of those slips would otherwise have reached the project finish (0.9 days).
  • The percent-complete note is where a reviewer will look first. One activity is 2% done after 22 working days, and its expected finish leaves it 6.4 days. At the rate so far it would need over 1,000.

This rests on one file, so it is thin evidence. If you have a P6 export that uses expected finishes, especially two updates of the same job, that is the check we want to run next. Everything runs locally: the tool never uploads the schedule.

Screening output, not scheduling, contractual or legal advice. Not affiliated with Oracle or Primavera; P6 is named only to describe the file format.