An owner's representative reading a contractor's monthly schedule update wants two answers. Is this update fit to rely on? And when the finish date moved, why did it move? XER Schedule Check already wrote the first answer up as a document you can print and send: corrections ranked high, medium and low, each with the activities behind it. Earlier today it also learned the second answer, a windows analysis across every update of a job. Until now the two did not meet. The analysis lived on the page and the review left it out.
Now they meet. Run the windows analysis on the job's updates, then print the review of the latest one, and the review gets a Delay by window section: each window's finish movement, how much of it came from progress and how much from revisions, and the activities on the driving path behind it. The section also adds two kinds of correction.
Revisions that moved the finish later. Say the contractor changed logic, durations, constraints or calendars between two updates, and the half-step run says those revisions alone moved the finish 7 working days. The review asks the contractor to justify each change it lists, and to say whether it is a change to the work or a correction of the plan. That is medium priority from a working week up and low below that. It does not say who is responsible. That is a matter for the contract.
Revisions that cancel a slip. This pattern is easier to miss. Progress on the driving path lost 7 days, and in the same update the remaining work was shortened or re-sequenced, which took 5 of those days back. The forecast finish moved only 2 days, so a reader who looks only at the finish date sees almost nothing. The plan holds on paper only if the compressed work really can be done faster. When revisions take back 2 or more of the days progress lost, the review asks for the recovery plan behind them and lists both the slipped work and the revision.
A big schedule has one more problem: a correction can sit on hundreds of activities. The body prints the first 40 of each. Until now the rest went in a CSV you had to send alongside. A new option adds an appendix that lists every one, so the PDF on its own is the complete record.
How it was checked
No public series of real monthly P6 updates exists, so we made some. We took the six public XER files used for every other check of this tool, from P6 5.0 to 24.12 and from 42 to 14,270 open activities, and used each one as the first update of a series. Each was statused "as planned" four times, 20 working days apart, with known changes planted in each window: a progress slip in window 2, a re-estimated activity on the driving path in window 3, and in window 4 a slip that a duration cut on later driving-path work partly cancels. Every update was written to disk as an .xer file, and the command line tool read the files in shuffled order and wrote the review with the appendix.
The results are in eval/review-windows-check-2026-11-19.md.
Writing the files to disk turned up a bug in the new XER writer. P6 Web exports store each calendar as one value that runs over many lines, and P6 Web wraps it in quotes. Our first writer dropped the quotes. The 24.12 file then read back with its calendars cut short, and its "as planned" window moved the finish 20.7 days when it should have moved none. The writer now quotes the value the way P6 Web does, and the 24.12 file reads back the same as the original.
What it is not
The section names candidate activities for each window. It does not say which party caused a delay, or whether a delay is excusable or compensable. Those questions belong to the analyst and the contract. The review is free, runs in your browser and never uploads the schedule. It is not engineering, legal or scheduling advice.