How P6 handles a lag after a finished activity: only the unspent part comes back

A rule found in a public P6 6.0 schedule: a finished activity's lag still counts backwards, but only the hours not yet run at the data date.

XER Schedule Check recomputes a Primavera P6 schedule's critical path in the browser and compares the result with the dates P6 stored in the same .xer file. On six public files it already matched early finish, late finish and total float on 19,820 of 19,822 open activities (the method). One set of numbers still did not match: the late dates P6 stores for activities that are already finished.

Why a finished activity has a late date at all

With retained logic, P6 keeps a completed activity in the network as a zero-length node at the data date, so logic still flows through it when work is done out of sequence. P6 gives that node a late date of its own and writes it to the file. In the heavily progressed CCA programme (P6 6.0, 14,270 open activities, 1,534 finished nodes with stored late dates), our engine agreed with 1,497 of them. The other 37 were all later than P6's dates.

What the 37 had in common

Listing them by successor showed six chains, each copying its error from one root activity. At each root the gap between P6's late date and a successor's late start was not random:

RootLinkLagWorked between actual finish and data dateP6's gap
PGLS103391C120FS into a finished node240 h8 h232 h
G02BM05501C0FS into an unstarted activity240 h8 h232 h
T20CO05305C0FF into a finished node48 h8 h40 h
PFNS103304R02FS into an unstarted activity96 h72 h24 h

In every case the gap is the lag minus the working hours that passed between the activity's actual finish and the data date: the part of the lag not yet spent.

The rule

Going forwards, a finished activity's lag runs from its actual finish, so a cure time still delays its successor. Going backwards, the engine used to take none of that lag off the finished node. That was right for lag that had already run out by the data date, and it is why an earlier test found "no lag back" correct. It was wrong for lag that is still running. Two other versions were tried and measured: taking the whole lag back loses 318 matches, and taking it back only into unstarted successors loses 231. Taking back the unspent part fits:

late date of a finished node = successor's late date − (lag − work from actual finish to data date), when that is positive.

With it, finished-node late dates match on 1,529 of 1,534 in the CCA file (1,550 of 1,555 over all six files), and not one open activity's dates or float changed. The rule is a switch (bwDoneLagLeft) in cpm.mjs, so the run without it can be repeated, and node eval/cpm-vs-p6.mjs now prints the finished-node count for each file.

What is still unexplained

The five left are one chain. Its root has a start-to-start lag of 312 h, used up in 2010, into an activity whose late date we compute exactly as P6 does, yet P6 puts the root 118.4 working hours after that date. Removing the link does not reproduce P6 either, so P6 honours it with some offset we have not found. The details are in eval/cpm-vs-p6-2026-11-19.md, rule 17 and "What is left".

Why it matters: a reviewer who sees a finished activity's late date move between updates should be able to tell whether the logic or the data changed. That only works if the tool computes those dates the way P6 does.

All writing · More in Tools and projects · All tools and research