XER Schedule Check recomputes a Primavera P6 schedule in the browser and checks its own dates against the ones P6 stored. On six public real P6 files it already agrees on 19,908 of 19,935 activities. The harder test is a public set of 338 small probe projects, each built around one awkward case and scheduled in P6 Professional 23.12 (danafitkowski/cpp-cpm-engine, validation/p6-probes). There the engine matched P6 on all four dates and both floats on 3,730 of 5,199 rows this morning.
The case
Activity A started Wednesday and has two days left. The data date is Friday at 17:00, the end of A's working day, so A's remaining work restarts Monday at 08:00. Activity B follows A by a start-to-start link and runs on a 24-hour calendar.
Where does B start? The engine said Monday 08:00: a start-to-start link waits for the predecessor's start, and A's remaining work starts Monday. P6, with the project set to progress override, says Friday 17:00. It does the same with a start-to-finish link, and with "lag from Actual Start" as well as "lag from Early Start".
The reading that fits every probe row: under progress override, a successor of work under way is laid from the data date itself. Any part of the lag not yet used up by the data date then runs on from there. A 40-hour lag that started Wednesday has 16 hours left on Friday evening, so B starts Tuesday at 17:00, which is what P6 printed. When A's remaining work happens no longer matters to B, so P6 also stops limiting A's free float at B. It prints 384 hours, running to the project finish, where the engine printed 0.
Under retained logic P6 does wait for the restart, and the engine already did that.
The result
| Before | After | |
|---|---|---|
| Probe rows matching P6 on all six values | 3,730 of 5,199 | 3,822 of 5,199 |
| Rows fixed / made worse | 92 / 0 | |
| Six real P6 files (early finish, late finish, total float) | 19,908 of 19,935 | 19,908 of 19,935 |
I also tested a third rule: under retained logic, count a start-to-finish link from the restart. One probe row suggested it. It fixed that row and broke nine others, so it ships switched off. The rules were fitted on these probes, so this isn't a held-out score. And no public real file has this setup, so the count on real files couldn't move. It didn't.
Why a scheduler should care
Free float and the start of the next activity are what an owner's scheduler checks first when a contractor's update lands, and a data date at the end of a shift is the usual case. A checker that disagrees with P6 here prints a different start and free float from the ones in the file, and the reviewer ends up chasing a difference P6 never made. The method, the probe rows and what's left are in eval/po-ss-data-date-2026-11-24.md. The tool runs free at marisstella.app, and nothing is uploaded.