A delay claim rarely has one event. A typical one has an owner's change, a late approval and a slow crew, and each party wants to know how many of the days are whose. The time impact analysis in XER Schedule Check already ran each event alone. That answer has a known problem: when two events delay the same path at the same time, their days alone add up to more than the delay with both in.
The usual answer is to put the events in one at a time, in the order they happened, and recompute after each. Each step is what that event adds on top of the ones before it, so the steps add up to the total. The tool now does that whenever a fragnet names two or more events. The order comes from the earliest Not before date on each event's rows.
The catch, measured
A stepwise split depends on the order. To see how much, the check planted two-event fragnets on six public P6 files, with answers worked out from plain one-activity runs instead of from the stepwise runs themselves (eval/tia-steps-check-2026-11-23.md):
- Events in series (one activity, then its only successor, both on the driving path): 19 of 19 split exactly as expected, and the same in either order. Each day reaches the finish in turn, so there is nothing to argue about.
- Events side by side (one event makes an activity longer, the other adds a parallel activity with the same links): 31 of 31 split exactly as expected, and all 31 split differently by order. The event that goes in second is charged only the days by which it outruns the first. Go oldest first and the later event is charged almost nothing. Go newest first and the older one is.
On the tool's built-in office fit-out, the owner's change adds 3 working days and the late hardware approval 6 more, 9 in all. Newest first, the hardware takes all 9 and the change takes none.
So the page, the CSV and the printable exhibit put the steps in date order next to the same steps run newest first and each event alone, and they say when the orders disagree. Then a reader can see that the split rests on a choice of order, not on the schedule's logic alone. Choosing the order, and deciding whether time or money is due for the overlap, is for the parties and their contract.
It runs in the browser on your own XER, and nothing is uploaded. The guide How to run a time impact analysis on a P6 schedule has the column layout. It has not yet been run on a real claim's dated event list. If you have one you can share, that is the next check.