Merging the site's constraints log with the P6 schedule: which late delivery moves the finish

Paste the materials, permits and RFIs log beside a P6 XER: each row gets its need-by date, a status, and how far it moves the finish if it clears late.

Every site meeting has two documents on the table. One is the look-ahead, cut from the Primavera P6 schedule. The other is the constraints log: a spreadsheet of the things the schedule doesn't hold. The rebar delivery, the inspection, the RFI the architect hasn't answered, the crew still on another job. Last Planner calls an activity "sound" only when both are clear: its predecessors are done and nothing on the log holds it.

The two rarely meet. The log has its own "need by" column, typed by hand from whatever the schedule said last month. So nobody can say at the table which of the twelve late items actually costs the job time.

XER Schedule Check now merges them. Open the XER, build the look-ahead, and paste the log (or open it as a CSV). The columns are found by name. Only the activity ID is required, and dates can be typed the way people type them.

What each row gets

  • Need by: the activity's remaining early start from the recomputed schedule, not last month's guess. For work already under way, it's now.
  • Latest start: the late start, past which a deadline moves.
  • Status: overdue (the promised date has passed and the row is still open), late (it clears after the need-by day), no date, on track, or cleared. Rows against finished work, and IDs not in the file, are named.
  • Days to spare, in working days on the activity's own calendar.

An activity that is ready by its logic but has an open row is now marked constrained, not ready.

The what-if

Then the question the meeting actually asks: if everything on the log arrives when promised, where does the finish land? Each open row's expected date goes into the CPM engine as a start floor on its activities. The same engine checks against P6's own dates on 19,820 of 19,822 activities. The schedule is recomputed, and the page gives the finish with the log next to the finish without it. Then each late row is run on its own, and the rows are ranked by how far each one moves the finish. That ranking is the list of calls to make first.

On the example schedule, three of the five open rows are late. Only the mechanical crew, promised for 4 May against a 17 April need, moves the finish, by two working days. The asbestos certificate and the stud delivery are both late too, but float absorbs them. Ranked, the crew row sits at the top.

How it was checked

Nobody publishes a real site's constraints log, so we planted them. We took six public P6 files, up to 40 rows each, and three seeds: 432 rows in all, 224 of them late. Then we computed the answer a second way: we wrote the same expected dates into the XER as P6 "start on or after" constraints and scheduled it from scratch.

  • The finish matched on 16 of 16 runs, and every open activity's dates matched on 59,334 of 59,334.
  • Each row's own finish slip matched on 128 of 128.

The first pass of that check did catch a bug. On the hotel file, nine as-late-as-possible activities came out with different starts, because the what-if was running only the forward pass, and ALAP early dates come from the backward pass. That's fixed.

The more interesting finding was about the late-start flag. On the 14,270-activity CCA file, 17 planted rows passed their late start without moving the project finish. The file carries negative float from interim date constraints, so those rows break an interim deadline while the end date holds. A what-if that only reports the finish would call them harmless, so the page shows both numbers. On the hotel file, two rows passed the late start without moving anything at all, with no deadline in sight. We haven't traced that yet, and the eval says so.

The log stays in the browser tab. The updated version, with the schedule's columns added, downloads as a CSV for next week's meeting. It's free, MIT licensed, and not professional advice: check the dates against the scheduling software of record before acting on them.