A resource sheet is not only the people and plant already on the schedule. Planners load the tower crane before its activities exist, keep a second concrete crew on the list in case the pour sequence changes, and write the hire terms in the resource's notes.
XER Schedule Check converts between Primavera P6's .xer and Microsoft Project's XML both ways. Going from Project to an XER, every resource made it into P6's resource table. Coming back from the XER to Project XML, only the resources an activity used were written. Anything unassigned disappeared on the second leg, and so did its notes and calendar. Nothing said so.
What changed
- A new option, write every resource in the file (a box on the page,
--all-resourceson the command line), writes the whole resource list. Resources with no assignment keep their calendar, notes and resource fields. No assignment changes. - The default still writes only the resources the project uses, as P6's own assignment views do, but it now prints how many it left out and names the option. Before, they went silently.
Measured
Every Microsoft Project XML file in MPXJ's public test corpus that has a work or material resource (66 files, Project 2002 to 2019) went to an XER and back:
| Only assigned resources | Every resource | |
|---|---|---|
| Resources back in Project XML (of 890) | 408 | 890 |
| Resource notes back, same text (of 17) | 6 | 17 |
On six public P6 files, the full list is 502 resources. 33 of them have no assignment in the exported project. All 502 come back from Project XML to an XER under the same resource ID, name and type. No assignment changed, and P6's import rules found no problem in any file written. The method, and what it doesn't check (opening the files in Project itself, and P6's resource hierarchy, which Project has no equivalent for), is in eval/all-resources-2026-11-21.md in the venture.
It all runs in the browser tab. The schedule never leaves your machine.