IFC Quantity Takeoff turns a building model into a bill of quantities in the browser. This morning's quality audit found a quiet hole in it. A steel beam's length and weight came only from the quantity set the exporter wrote. When the exporter wrote none, the line said 0 m and 0 kg, and a rate per metre or per kilogram priced the beam at nothing.
How often that happens
On 30 public IFC models (the method and every number), 4,952 of 10,035 columns, beams, members and piles store no Length. That is about half. Whole models have none at all: the 1,585 members in advanced_model, the 1,209 in ISSUE_098 and the 534 in dental_clinic.
The fix is the definition in the standard. Qto_BeamBaseQuantities defines Length as the total nominal length, "not taking into account any cut-out's or other processing features". That is the body's extent along its extrusion, so the tool now reads it from there. 4,948 of the 4,952 got a length. The other 4 have no axis to read.
Checking it against the members that do store one
A computed figure is only worth summing if it agrees with the stored ones. Of 5,083 stored Lengths, 4,153 agree within 2%, including all 1,649 in the HHS Office models and 2,138 of 2,203 in a Tekla steel model.
Most of the rest came from one model, and those turned out to be the more useful finding. In ARK_NUS_skolebygg (Revit), 603 curtain-wall mullions each store 20.858 m, the length of the facade they belong to, while their bodies are 0.4 to 3.5 m long. Together they stored 5,480 m of mullion against 795 m of actual mullion. The bill of quantities had been summing the stored figure, which overstated the line about 6.9 times.
The tool now names the cause ("host-figure"): one stored Length on three or more members of the same assembly, all shorter than it and differing from each other. For those members it sums the body instead. 327 pairs still disagree with no named cause (mostly Tekla diagonal braces, whose stored figure is a reference-line length). They keep their stored figure and are listed in the eval.
Weight
Steel is priced per tonne, so a beam also needs a weight. For a member whose material names plain steel (S235 to S690, ASTM A36/A992, "Steel - Structural", "staal" and so on), with nothing in it naming concrete, timber, stainless or rubber, the weight is the volume times 7,850 kg/m³. That density is in the Eurocode tables and matches AISC's 490 lb/ft³. Two Tekla models store weights to compare against, and the density agrees with 230 of 233. The 3 misses are beams Tekla weighed from a simplified section, a cause the tool already scales. 512 steel members that weighed 0 kg now weigh what they should.
Two catches along the way. Tekla's "STEEL/NEOPRENE" bearing pads matched the first steel pattern, so rubber is excluded now. "05 Staal_bordes_hoeklijnen" (Dutch: steel landing angles) didn't match at all, because the underscore glued the words together.
What it does not do
The weight is the solid's, so bolts, welds and the connection allowance an estimator adds are not in it. Stainless steel is left unweighted rather than guessed. A member whose only material name is a paint colour (829 ARK_NUS members say "RAL 9004") is not weighted either. Each bill-of-quantities line now says how many of its lengths and weights were computed and how many are still missing, so nothing silently prices at zero.
The same change added tests for three geometry branches the audit's seeded bugs had slipped past: an elliptical profile, a revolve axis away from the origin, and centimetre units. All three seeded bugs now fail the suite.
The tool is free and runs in the browser: marisstella.app/ifc-quantity-takeoff. Results are estimates to check, not professional advice.