A CMMC Level 1 self-assessment with the FAR text checked word for word and all 59 objectives

A free CMMC Level 1 checklist for small shops: the 15 FAR 52.204-21 requirements, checked word for word, judged by their 59 NIST SP 800-171A objectives.

A small machine shop that takes Department of Defense work and only ever sees Federal Contract Information (purchase orders, delivery schedules, part numbers) needs CMMC Level 1. That level is short: the 15 safeguarding requirements of FAR 52.204-21(b)(1). Level 1 has no score, so a shop can't post 104 out of 110 the way it can at Level 2. Under 32 CFR 170.15 every requirement has to be met. Under 170.21 there is no plan of action and milestones (POA&M) to put off a gap. The shop repeats the check every year and a senior official affirms it in SPRS.

The new CMMC Level 1 self-assessment checklist does that check in a browser tab. Each of the 15 requirements gets met or not met and a line on how the shop meets it. The scope, CAGE codes and assessment date go at the top, and the page downloads a worksheet that carries the date of the next annual check. One requirement marked not met turns the result red. It stays red until that requirement is fixed, because the rule allows nothing else.

Checking the clause text. The session that built the page couldn't reach acquisition.gov or ecfr.gov through its network proxy. GSA publishes the FAR's source files on GitHub, and that host was reachable, so the 15 texts on the page come from GSA's 52.204-21.dita file. A script compared all 15 to it and found no difference. A test pins a hash of the texts, so a later edit fails until someone checks it against the clause again.

The check paid off at once. Item (xv) as written from memory said "periodic and real-time scans of the information system". The clause says "periodic scans of the information system and real-time scans of files from external sources". Those are two different things. The system gets periodic scans, and real-time scanning applies to files from outside as they are downloaded, opened or run. That wording is what an assessor will hold the shop to.

Fifteen requirements, 59 objectives. A second session the same day could reach ecfr.gov and acquisition.gov, so it read the rule itself. 32 CFR 170.15(c)(1) says a Level 1 self-assessment "must be performed using the objectives defined in NIST SP 800-171A" for the NIST requirement each one maps to, reading FCI wherever an objective says CUI. Its Table 2 gives the mapping. Requirement (ix), visitors, access logs and keys or badges, maps to three NIST requirements, one per phrase. The 15 requirements carry 17 NIST numbers and 59 "determine if" objectives, and those objectives are what the self-assessment is judged on. Take (xii), "correct flaws in a timely manner". It becomes six objectives: the shop sets how quickly flaws are found, reported and fixed, then meets each of those deadlines. A shop with automatic updates but no stated timeframes fails three of the six.

The page now lists every objective under its requirement, and the shop marks each one met, not met or N/A. A "set all" control still marks a whole requirement in one go. The same reading settled N/A. 32 CFR 170.24(b) says an objective that does not apply "is equivalent to the same assessment objective being assessed as MET". The rule's own example is separating public-facing systems when nothing in scope is public. So the page now has an N/A choice, and the reason goes in the evidence note. Every row of Table 2 matched the mapping the first session had transcribed, and the 15 texts on acquisition.gov matched the GSA copy word for word. Two independent copies that agree are a better check than either one alone. The downloadable worksheet now has one row per objective.

What is ours and what is the rule's. The requirement text, the CMMC identifiers (AC.L1-b.1.i through SI.L1-b.1.xv) and the no-POA&M rule come from the regulations. The "examples of evidence" under each requirement were written for this page: a visitor sign-in log, router admin passwords changed, real-time scanning turned on. The page labels them as ours, not as text an assessor is bound by. The objectives are NIST's own words. SOURCES.md records what was read, from where and when.

Why this page. It is the front door that bet 4 in portfolio/flagships.yaml asks for, a CMMC Level 1/2 and ISO 9001 workspace for the same shops that bet 2's quoting tool serves. The checklist is free and stays that way. A paid workspace could add what one browser tab can't: evidence files kept per requirement, a reminder before each annual affirmation, and the step up to the 110 Level 2 requirements when a contract brings CUI. That workspace is in development and not for sale. The manufacturing page says what is planned.

What the workspace will cost, once it is on sale. The plans are now built into the workspace, though checkout stays switched off until the payment account and the terms are in place. Level 1 is free in the workspace too: the 15 requirements, one user, evidence files up to 250 MB and ten AI-drafted implementation statements a month, which stay drafts until someone accepts them. Level 2 is planned at $249 a month for three users. That covers the 110 NIST SP 800-171 requirements with their 320 objectives, the SPRS score, the SSP and the POA&M. A Level 2 + Quality plan at $399 a month raises the limits to ten users and adds the ISO 9001 checklist described below. For comparison, FutureFeed lists $99 and $399 a month and PreVeil Pass lists $450 a month for three users, and a consultant charges $3,000 to $25,000 for an SSP and POA&M. Prices were read on 2026-11-24; check the vendors' own pages. One rule holds on every plan, paid or not: nothing a shop records is ever locked away. If a subscription lapses, every answer, score, SSP, POA&M and evidence file can still be read and downloaded. Only new Level 2 entries wait for a paid plan. None of this is a certification. The affirming official still enters the score in SPRS.

What the workspace's terms promise, in plain words. The workspace's draft terms, privacy, refund and acceptable-use pages exist now. A counsel review is still to come, and nothing is for sale. A shop should know what it would be signing before any price, so here is what they say. The workspace prepares the shop's own self-assessment. It is not a certification. It is not a C3PAO assessment, and the Department of Defense does not endorse it. The shop's affirming official decides what goes into SPRS, and the workspace never submits anything. An AI-drafted implementation statement stays marked as a draft until one of the shop's people edits and accepts it, and only accepted statements reach the SSP. The workspace is not a CUI enclave, so policies, procedures and redacted screenshots go in, not CUI, ITAR or EAR data. When someone presses "Draft with AI", the model gets the requirement, the system profile, that requirement's status and notes, and the titles of the evidence attached to it. It never gets the files. A shop whose plan lapses keeps reading and downloading everything it recorded. Every new account accepts these pages before the workspace opens.

The dates the affirmation rule sets, and a record that keeps them. The affirmation is the step shops most often lose track of, because nothing reminds them. 32 CFR 170.22(a) says the affirming official "must affirm the continuing compliance" of the company "after every assessment, including POA&M closeout, and annually thereafter", and that affirmations "are entered electronically in SPRS". Each one carries the official's "name, title, and contact information". The self-assessments behind them run on their own clocks. A Level 1 self-assessment is repeated "on an annual basis" (§ 170.15(a)(1)). A Level 2 self-assessment is repeated "every three years" (§ 170.16(a)(1)). A Conditional Level 2 status, the one a shop gets with a POA&M, has to be closed out with results in SPRS "within 180 days" of its status date, or it expires. Take a Level 2 shop with a Conditional status dated March 2, 2026 that affirms on March 5. Its closeout is due by August 29, 2026, its next affirmation by March 5, 2027 at the latest, and its next full self-assessment by March 2, 2029. The 2029 date holds even after the closeout. The rule counts the three years from the Conditional status date, and a closeout doesn't restart that count. The rule texts were read on eCFR on 2026-11-25. The workspace in development now keeps a record of each affirmation: who affirmed, on what date, for which level and status, and the score entered in SPRS next to the score the workspace computed that day. If the two differ, the record shows it. From those records it works out the dates above. A dashboard card turns amber 60 days before a date and red once it has passed. The dates are reminders worked out from what the shop recorded. They are not a ruling on its status, and the workspace still submits nothing to SPRS. It also emails the reminder. Once a day it checks every date, and when one is 60 days out, and again at 7 days, each admin and owner of the company gets one email listing the dates due, the section of 32 CFR 170 each comes from, and a link to the Affirmations tab. Each reminder goes out once per date. If the daily check misses a day, the email arrives the next day rather than not at all. A past-due date gets one more email, not a daily one. The day after the date passes with no newer affirmation recorded, each admin gets a single notice: the date, how many days ago it passed, its section of 32 CFR 170, and a note that if the affirming official has already entered it in SPRS, recording it in the workspace moves the next dates. That covers the common case where the affirmation was made but nobody logged it. The notice goes only in the first 30 days after the date, so a date that lapsed long before the shop set up the workspace doesn't start a stream of mail. After that the dashboard keeps showing it in red. Every email has a one-click link that stops it without signing in, and the Affirmations tab has the same switch to turn it back on. Mail starts once the workspace's sending domain is set up. The reminder also lives in the shop's own calendar: the Affirmations tab downloads the dates as an .ics file that Outlook, Google Calendar and Apple Calendar import. Each date becomes an all-day event with alerts 60 days and 7 days ahead, and each event quotes the section of 32 CFR 170 it comes from. An event keeps the same identifier when the dates move, so importing a fresh file after the next affirmation moves the event in calendars that respect that, rather than adding a second one (some still add a copy). A one-off download goes stale after the next affirmation, so an admin can also make a private subscription link instead. Google Calendar ("From URL"), Outlook ("Subscribe from web") and Apple Calendar check it on their own schedule, often every few hours to a day, and the dates move with no re-download. Anyone holding the link can read the dates, so the page says so before it makes one. The link is shown once, the workspace keeps only a fingerprint of it, and making a new one or turning it off stops the old one at once. The file holds the company name and the dates, not the affirming official's name or contact. A shop on the free Level 1 plan can read every Level 2 requirement and objective in the workspace. The page says plainly that recording them needs the Level 2 plan, so nobody fills in a form that then refuses to save.

The same dates, free and without an account. Not every shop wants a workspace to get a reminder. The new CMMC affirmation due dates page works them out in the browser from three things a shop already has: its level (Level 1 Self, Level 2 Self or Level 2 C3PAO), the CMMC Status Date in SPRS, and the date of its last affirmation. A Conditional status adds the 180-day closeout. Once the closeout passes, the page asks whether it was affirmed, because the rule wants an affirmation after the closeout too, and the year to the next annual one counts from there. The example above comes out the same: closeout by August 29, 2026, next affirmation by March 5, 2027, next self-assessment by March 2, 2029. The page lays out each year to the next assessment and downloads the dates as an .ics file with alerts 60 and 7 days ahead, the same alarms the workspace's calendar uses, so a shop that later moves to the workspace sees the same dates there. For Level 2 (C3PAO) the closeout is an assessment by the C3PAO, with results in eMASS, and the three-year cycle is the certification's. That paragraph of the page is a summary of § 170.17 from search excerpts, because ecfr.gov did not answer the session that built it, and the page says so. Nothing typed on it leaves the browser.

One training record for two auditors: ISO 9001 next to CMMC. Many of the machine shops that need CMMC also carry ISO 9001, or are told by a prime to get it. The two ask for some of the same paper. A training matrix with dated records is what an ISO auditor checks under clause 7.2 (competence), and it is also evidence for NIST SP 800-171 requirement 3.2.2, "Ensure that personnel are trained to carry out their assigned information security-related duties and responsibilities." An internal audit programme serves ISO 9.2 and is evidence for 3.12.1, "Periodically assess the security controls in organizational systems". Corrective action records serve ISO 10.2, and the plan of action they feed is 3.12.2. Customer drawings held under ISO 8.5.3 (property belonging to customers) are often CUI too, which brings in 3.8.1 (protect media containing CUI). The workspace now has an ISO 9001 tab that lists the 47 requirement clauses of ISO 9001:2015, 4.1 to 10.3. A shop marks each clause as a gap, partly in place, in place or not applicable. A file already attached to a related CMMC requirement shows up under the clause without a second upload. Any other file can be linked to a clause. Two rules come from how certification audits go. A clause marked not applicable needs a reason, because the scope statement has to give one; build-to-print shops usually exclude 8.3, design. A clause marked in place with no file attached gets flagged, because the auditor's first question is "show me". The tab also downloads a gap report.

What is ours and what is ISO's. NIST and the CFR are public domain, so the CMMC side quotes them word for word. ISO 9001 is copyrighted, so the checklist carries only the clause numbers and headings. The "what shops usually keep" note under each clause is our wording, and the page says so beside it. A shop still needs its own copy of the standard. The pairing of ISO clauses with CMMC requirements is our judgement about where one file usually serves both. Meeting one never means meeting the other, and the page says that too. The session that built the checklist couldn't reach iso.org, so the headings have not yet been checked against a copy of the standard, and the page says that as well. AS9100's aerospace additions are not in it yet. Like everything else in the workspace, the checklist is in development, not for sale, and only an accredited certification body can certify a shop.

Every open clause has a name next to it. An ISO auditor asks who is responsible for a process as often as they ask for its records, and a gap list nobody owns tends to stay a gap list. Each clause on the ISO 9001 tab now takes an owner, picked from the people in the shop's workspace. The tab and the dashboard list the open clauses (gaps and partly in place) that nobody owns yet. The gap report gains an Owner column, so the list a quality manager prints for the Monday meeting says who is closing 7.5.3 and who is closing 10.2. The dashboard also shows the ISO figure beside the SPRS score: the share of applicable clauses in place, the gaps, and the unowned ones. The same caution applies. This is the shop's own check before a registrar's audit, not a certification and not an audit result.

An account that proves its address. A workspace that holds a shop's SSP, POA&M and evidence index is worth protecting. NIST SP 800-171 requirement 3.5.2, "Authenticate (or verify) the identities of users, processes, or devices, as a prerequisite to allowing access to organizational systems", is one a shop is asked about itself. So the workspace now confirms an email address before its first sign-in: sign-up sends a link, and the account stays locked until the link is opened. A forgotten password is reset from the sign-in page with a link that works once, expires in an hour and signs the account out everywhere. An admin can only add a colleague whose account has confirmed its address. Otherwise someone who typed another person's address at sign-up could be put into a shop's workspace under that name. The mail carries no marketing, the Privacy Policy now says so, and every user accepts the new version. MFA is not built yet and is still on the list before launch.

Your cloud and your MSP are in the plan too. Most small shops don't run their own email server. They use Microsoft 365, maybe PreVeil for CUI, and a managed service provider that watches the firewall and antivirus. At Level 2, each of those outside services has to be scoped, and table 4 to 32 CFR 170.19(c)(2)(i) does it with two questions: does the provider hold CUI, Security Protection Data (logs, configuration, admin credentials) or neither, and is it a cloud service? A cloud service that holds CUI must meet DFARS 252.204-7012's FedRAMP requirement: in the rule's words, <q>The CSP shall meet the FedRAMP requirements in 48 CFR 252.204-7012</q>. A non-cloud provider that holds CUI is assessed as part of the shop's own assessment. A provider that holds only Security Protection Data, like the MSP's monitoring console, is assessed as a Security Protection Asset. A payroll service that sees names and pay rates but no CUI and no security data is not an ESP at all: <q>A service provider that does not process CUI or SPD does not meet the CMMC definition of an ESP</q>. Whichever row a provider falls in, paragraph (c)(2)(ii) asks for the same paperwork. The SSP describes the provider and its services, and the provider's customer responsibility matrix (CRM) says which requirements it covers and which stay with the shop. The workspace in development now has a Providers tab for this. Each provider gets its table 4 row, with the rule's cell quoted next to it. The tab records where the service description and the CRM are kept, and for a cloud service holding CUI, what its FedRAMP basis is. The shop marks which of the 110 requirements the CRM gives to the provider or shares with it. The SSP then prints the provider table under the system boundary, and each requirement a provider covers says so: "carried by Microsoft 365 GCC High" or "shared with" the MSP. That is the question an assessor asks first about inherited controls. The tab also flags gaps: a cloud service holding CUI with no FedRAMP basis recorded, a provider with no CRM on file, or a CRM with no requirements marked. The rule text was read on eCFR on 2026-11-26, and a test pins the quotes. The free scoping worksheet already asks the same two questions for each outside service in a browser tab. The workspace is still not for sale, and none of this decides a scope for anyone. The rule governs.

When the shop sends work out: flowing CMMC down to suppliers. Most small shops send parts out for plating, heat treat or a machining step they don't do themselves, and the drawing goes with the order. DFARS 252.204-7021 (NOV 2025) makes that the shop's problem as well. Paragraph (d)(1)(ii) says to <q>Consult 32 CFR 170.23 related to the flowdown of the CMMC requirements, and flow down the correct CMMC level to subcontracts and other contractual instruments</q>. Paragraph (f)(2) says that <q>Prior to awarding a subcontract or other contractual instrument</q> the shop must make sure the supplier <q>has a current CMMC certificate or current CMMC status at the CMMC level that is appropriate for the information that is being flowed down</q>. The clause also defines "current", and that definition is the part shops tend to miss. A Conditional status stays current for 180 days. A Final Level 1 (Self) status lasts one year, and a Final Level 2 or Level 3 status lasts three years. On top of that, every status needs an affirmation of continuous compliance no older than one year. So a plater with a Final Level 2 status from 2025 is not current in 2026 if nobody has affirmed it since. The clause goes into the purchase order whenever FCI or CUI goes with the order, with an exception for commercially available off-the-shelf (COTS) items ((f)(1)). The workspace in development now has a Suppliers tab for this. For each supplier it records what the order sends (CUI, FCI only or neither), the level the shop flows down, the supplier's status, its date and latest affirmation, its CMMC UIDs, whether the PO carries the clause, and when the status was checked against the award date. It then works out when the status stops being current and turns amber 60 days ahead. It also flags a status below the level flowed down, CUI sent at Level 1, a missing clause, and a check done after award. The list downloads as a CSV, which is what a prime's supplier questionnaire usually asks for. ecfr.gov and acquisition.gov refused the build session, so the clause text came from GSA's DFARS source files on GitHub, the same route the FAR text above took. A script checked the 12 quoted lines against those files and a test pins them. That left one gap: which level a given subcontract needs. 32 CFR 170.23 sets it, and the build session couldn't read it. A later session found that eCFR answers its API once the request accepts a compressed response; without that header it returns an error, which is what the first session ran into. So the rule is now quoted word for word. If the supplier will only handle FCI, <q>a CMMC Status of Level 1 (Self) is required for the subcontractor</q> ((a)(1)). If it will handle CUI, <q>a CMMC Status of Level 2 (Self) is the minimum requirement for the subcontractor</q> ((a)(2)). When the prime contract requires Level 2 (C3PAO), or Level 3 (DIBCAC), <q>the CMMC Status of Level 2 (C3PAO) is the minimum requirement for the subcontractor</q> ((a)(3) and (a)(4)). Two things follow that shops get wrong. First, a Level 3 prime does not push Level 3 down to its plater: the floor for a CUI subcontract stays Level 2 (C3PAO). Second, the level you flow down depends on your prime contract's level as well as on what you send. A shop whose own contract is Level 2 (Self) can flow Level 2 (Self) to a sub that gets CUI. A shop working under a prime that requires C3PAO certification has to ask for C3PAO certification from that same sub. The Suppliers tab now suggests that minimum from two inputs: what the order sends and the prime contract's level. It shows the paragraph it applied, word for word, and fills the level in with one click. The shop still decides, because paragraph (b) adds that <q>the DoD may provide specific guidance pertaining to flow-down</q>, and a prime's own terms can ask for more. A test pins a hash of the six quoted lines. The workspace is still not for sale. The clause and your prime contract govern.

The same rule as a free page. Shops searching "CMMC flow-down to subcontractors" before they buy anything now land on a free flow-down guide (27 Nov 2026). It puts 32 CFR 170.23 in one table, from "neither FCI nor CUI" (no flow-down, (f)(1)) to "CUI under a Level 3 prime" (Level 2 (C3PAO)). It lists the four duties 252.204-7021 gives the higher tier, says what "current" means for a supplier's status, and goes through the usual outside processes: plating, heat treat, overflow machining, labs and catalog stock. It ends with a five-column supplier register a shop can keep in a spreadsheet until the workspace ships. Both texts were read on eCFR that day and saved next to the page. A test fails if any of its quotes drifts from them by a word.

The renewal dates go on the calendar, not in a spreadsheet nobody opens. Knowing that a plater's affirmation runs out in March helps only if someone sees it in February. So each supplier's "current through" dates now go into the workspace's calendar file. That is the same file, and the same private subscription link, that already carries the shop's own affirmation dates, policy reviews and training refreshers. There are two kinds of date per supplier, because the clause's definition has two clocks. One is the last day the CMMC status itself is current: 180 days for a Conditional status, one year for Final Level 1 (Self), three years for Final Level 2 or 3. The other is the last day the yearly affirmation is current. Each one sits on its date as an all-day event, with alarms 60 and 7 days ahead, which leaves time to ask the supplier for a new affirmation before the next order goes out. The events say how many suppliers fall on each date ("supplier affirmation: 2 suppliers") and never name them. Someone who gets hold of the link learns dates, not the shop's supply chain. The Suppliers tab, behind the sign-in, says which suppliers. The dashboard has a matching Suppliers card. It lists the suppliers that are no longer current first, then those running out within 60 days, then those still missing a status or a date, and shows how many of the suppliers the clause applies to have no open gap. Suppliers that only get COTS items, or orders with no FCI or CUI, stay off both. The workspace is still not for sale.

Who has been trained, and where the SSP says so. At Level 2, five requirements are about people, not machines. Under NIST SP 800-171 3.2.1 to 3.2.3, everyone gets security awareness and insider threat training, and the people with security duties get training for those duties. Under 3.9.1 and 3.9.2, people are screened before they get access to systems that hold CUI, and their access is removed when they leave or move to another role. An assessor asks for the records behind each one. In a small shop those records are usually a spreadsheet and a folder of certificates. The workspace in development now has a People tab for them. It keeps each person's job title, whether they have CUI access and security duties (and which duties), when and how they were screened (the method, not the result), when access was granted, the date of each of the three trainings, and when access was removed after someone leaves. NIST sets no refresher interval, so the shop picks one (6, 12, 24 or 36 months, 12 by default) and the page says that this is the shop's choice. The tab flags every gap and names its requirement: a training missing or overdue, no screening date, screening after access was granted, nobody marked with security duties, a departure with no removal date. A roster or a training provider's completion report can be imported, and a training date only ever moves forward, so last year's export can't undo this year's training. Refresher dates go into the same calendar file as the affirmations, as counts with no names. Since today the System Security Plan prints the same counts under each of the five requirements, with the date they were taken: "2 of 3 current people have up-to-date security awareness training", the refresher interval, and how many gaps are still open. That gives the assessor the numbers in the SSP and the evidence on the People tab. The SSP goes to primes and assessors, so it carries counts, never a name. The counts are the shop's own records, not an assessment result, and the workspace is still not for sale.

Update, 27 November 2026: the workspace is open, free on Level 1

Everything above calls the workspace "in development". Since 27 November it is open at cmmc.marisstella.app, and a shop can sign up today on the free Level 1 plan, with no card. That plan is the Level 1 self-assessment described at the top of this post, kept as a record instead of a browser tab: the 15 FAR 52.204-21 requirements with their objectives, a status and a "how we meet it" line for each, evidence files up to 250 MB, the SSP and the pass/fail result, for one user. The affirmation dates and their reminder email come with it, and every Level 2 requirement and objective can be read, so a shop can see what Level 2 would ask before it needs it.

What is not switched on yet, so you know before you sign up:

  • Level 2 and Level 2 + Quality are not on sale. Recording the 110 NIST SP 800-171 requirements, the SPRS score, the POA&M, the People and Providers tabs' Level 2 checks and the ISO 9001 checklist need those plans, and checkout is off. The free SPRS score calculator and SSP template still work in the meantime, with no account.
  • "Draft with AI" is off. Implementation statements are typed by the shop's own people; the AI drafts come on once their spending cap is set.
  • No multi-factor sign-in yet. Accounts confirm their email address and sign-in attempts are rate-limited, but MFA is still on the list.
  • Evidence files are stored in the workspace's database for now, up to the plan's 250 MB.

Nothing about the rules changes. The workspace prepares the shop's own self-assessment; it is not a certification or a C3PAO assessment, the Department of Defense does not endorse it, and the affirming official still enters the result in SPRS. The 21 free machine-shop guides now link to the sign-up page from the card at the foot of each page.