Why a framing bid total said Infinity, and a permit vanished

A wall-framing takeoff budget accepted Infinity as a price and silently dropped text or negative allowances. It now refuses and lists them.

The wall-framing takeoff turns a house plan into a lumber order and a budget from prices you type. Probing it with hand-typed junk found two quiet failures.

  1. Absurd prices went straight into the total. A labor rate of Infinity gave a total of Infinity, and 1e300 gave 2e302. The old check was only "is a number, not negative".
  2. Bad allowances disappeared. A permit typed as "500" (text) or -1 was skipped with no message, so a bid could leave out a lump sum and look fine. Prices had a "did you mean" note for misspelt names, but not for bad values.

Now a price or allowance must be a finite number from 0 to 1,000,000,000. Anything else is left out of the total and listed in the report ("values refused ... allowance permit = \"500\""), and in the JSON as refusedValues. The cap is a guard against typos, not a pricing rule. A zero price is still legal.

Checked with a new test across Infinity, NaN, 1e300, negatives, text, true and objects; the full 729-test venture suite passes. All inputs were invented, not a real contractor's bid.