What happens to the framing schedule when the crew is on another job?

The wall-framing schedule page now takes a crew's days off and shows how far the finish date moves.

A small framing outfit rarely has a crew to itself. Three days pulled onto another site in week one can move the whole completion date, because every later activity waits behind that crew.

The schedule page of wall-framing-takeoff now has a Crew days off field. Type concrete=2026-03-02 2026-03-03 2026-03-04 and that crew's activities pause on those days; other crews are untouched. In the page's sample schedule those three days moved the last date from 2026-04-28 to 2026-05-01. The engine supported this already; only the command line could reach it.

The dates are your own calendar. The tool ships no durations and no crew records, and the result is a planning aid, not a promise. It was checked by clicking the field in Chromium, not against a real builder's schedule.