Concrete maturity is a new free tool in the construction set, beside wall framing takeoff. It answers the question a superintendent asks after every cold-weather pour: is it strong enough yet to strip the forms, cut the joints or stress the tendons?
What it does
Concrete gains strength faster when it is warm. The maturity method (the US standard practice is ASTM C1074) turns a temperature record into one number, the maturity index, so that concrete with the same index has about the same strength. You learn how strength rises with the index once per mix, from lab cylinders broken at several ages, and then any logger buried in that mix tells you roughly how strong the concrete around it is.
The tool takes the two files a site already has: the logger's CSV export and the lab's break results. It
- reads the CSV (US or ISO timestamps, or elapsed hours; °F or °C; several sensors; semicolon files with decimal commas), skipping humidity and battery columns;
- computes the maturity at every reading by Nurse-Saul (degree-hours above a datum) or equivalent age (the Arrhenius form);
- fits three strength-maturity curves to the breaks (logarithmic, hyperbolic, exponential), shows R², RMSE and AICc for each, and uses the lowest AICc unless you choose;
- reports each sensor's estimated strength now, when it reached the target, or how long it should take at an assumed temperature, with warnings for freezing, hot early curing and extrapolation past the oldest specimen.
It runs in the browser; nothing is uploaded. A command-line version does the same in a script.
Why every sensor, not one
The made-up example on the page is a slab placed at 2 pm on a cold November day with a logger at mid-depth and one near an exposed edge. After five days the mid-depth logger reads about 2,650 psi on the example's curve, and the edge about 2,170. Against a 3,000 psi target, mid-depth needs about 2.7 more days at the last day's temperature and the edge about 7.2. A decision made on the warm core alone would strip concrete the record says is over 800 psi short at the edge. The tool marks the lowest sensor as governing for that reason.
These numbers come from invented data, generated by a function in the source and labelled as such on the page. No real project's record has been run through the tool yet; that is the next thing it needs.
What it is not
It is an estimate, not a determination. The curve belongs to one mix, and it assumes the concrete stayed moist enough to keep hydrating. The standard itself asks for the estimate to be confirmed by other tests before critical operations such as form removal or post-tensioning, and the engineer of record decides what evidence is enough. Commercial maturity systems sell wireless sensors, project records and a vendor to stand behind the process; this is for the case where you already have the file and want to see the arithmetic.
Next on its list: working out a mix's datum temperature and activation energy from mortar-cube tests at three temperatures, and readers for named logger formats as real exports turn up.