The free XER Schedule Check recomputes a Primavera P6 schedule from its logic and compares the result with the dates and float P6 stored in the file. On six public XER files (P6 5.0 to 24.12, 19,822 open activities) it already agreed on early finish, late finish and total float for all but 2. Free float, the slack an activity has before it delays anything else, was behind: 19,810.
Nine of the misses sat in one file, a P6 24.12 Web export. In each one, the file's own dates left a clear gap before every successor. Activity A10590 finishes on 11 November at 16:12. Its only successor starts on 20 November at 08:00, in P6's stored dates and ours. That is 48.8 working hours of free float. P6 stored 0.
Yesterday's note on this put it down as unexplained and left it alone rather than fit a rule to it. Today we looked at every field on the nine. They have nothing obvious in common: five are started and four are not, their links are finish-to-start, start-to-start and finish-to-finish, one has no successor at all, and none was edited after P6's last schedule run. What they do share is an expected finish date. The project has P6's "use expected end dates" option on, and a scheduler typed a date on each of them.
The split is clean on that file:
| Open activities in the 24.12 file | Count | P6 stores |
|---|---|---|
| expected finish set | 23 | 0, on all 23 |
| ... and a positive gap in the dates | 9 | 0, on all 9 |
| no expected finish, positive gap | 72 | the gap, on all 72 |
So the engine now gives free float 0 to any open activity with an expected finish when the project uses them. Free float matches P6 on 404 of 404 in that file and 19,820 of 19,822 overall. The two still off are activities whose early dates already differ, behind a lag someone lengthened after P6's last run.
We have a reading of why: an expected finish tells P6 the activity ends on that date, and P6 sizes the remaining duration to hit it, so it shows no room to slip. But we didn't find this in Oracle's documentation, and it comes from one file and one P6 version. Of the other five files, none stores an expected finish. If you have an XER from P6 8 to 23 with expected finishes, it would show whether older versions do the same.
Why it matters: free float is the number a reviewer uses to see what an activity can slip without touching its neighbours. If a checker gives 48 hours where P6 gives none, the reviewer gets two answers and has to work out which one is right. The schedule CSV download now gives P6's answer.
Method and every count: eval/free-float-expected-2026-11-20.md. The tool runs in the browser and nothing is uploaded. Its results are screening aids, not professional scheduling advice.