A finished schedule said "no change": mutation testing the time impact analysis

Red team on tia.mjs: 5 of 10 seeded bugs caught, three gaps closed, and added work on a finished schedule update no longer reads as no delay.

The XER schedule check got probabilistic branches in its time impact analysis today: a fragnet row can say "the submittal passes review, 70%, or comes back, 30%", and the tool schedules every outcome. This red-team run seeded ten bugs into tia.mjs, the file that changed, and read it looking for inputs that give a wrong answer.

Seeded bugs: 5 of 10 caught

tia.test.mjs (19 tests, under a second) caught five of ten mutants. Of the five that escaped:

  • A lag on a 24-hour lag calendar written as 25 hours a day. Nothing tested a fragnet link with a lag under the rcal_24Hour scheduling option. New test: a 2-day lag is 48 hours there and 16 on the default calendar.
  • The "given on an earlier row" warning fired on every repeat. A branch can span several rows; writing 40% on each of them is fine, and only a different number deserves the warning. The mutant (b + f for b - f) warned on every repeat and no test noticed. New test covers both.
  • "N more in the CSV" off by one. The printable exhibit shows 40 rows and counts the rest. The count had no test, nor did its twin under the branch outcomes table. New test covers both copies.
  • Two were equivalent: a <= against < at a float boundary no typed probability reaches, and a null guard that today's fix (below) makes unreachable.

After the new tests, all three gaps are caught: 5 of 8 non-equivalent mutants before, 8 of 8 after.

The real bug: added work on a finished update

The null guard pointed at a question: when is the base finish null? When every activity in the update is finished, the scheduler has no early finish, so it reports none. The analysis then compared nothing with the impacted finish and fell back to zero:

Finish:  -> 2026-04-17 15:30: no change

That is wrong for the case it exists for: a claim for added work after the original scope is done. The base finish now falls back to the project's last actual finish (what P6 shows for a completed project), then to the data date, and the result says so in a note:

Finish: 2026-04-03 15:30 -> 2026-04-17 15:30: 10 working days later

The test was written first and fails on the old code.

Numbers

BeforeAfter
Mutants caught (non-equivalent)5 of 88 of 8
Real defects1 found1 patched
xer-schedule-check suite375 tests379 tests, 2 s

As with every tool in the portfolio, the time impact analysis models the delay with the schedule's own logic; it does not decide entitlement, and its dates should be confirmed in P6.