XER Schedule Check reads Primavera P6 .xer exports in the browser. It now has a Find redundant logic button.
A relationship is redundant when another chain of links already says what it says. If A finishes before B starts and B finishes before C starts, a link from A to C cannot move C, however long A, B and C turn out to be. Schedules collect these: a fragnet tied both step to step and to its start, a block copied with its links and then re-tied. P6 shows driving and non-driving links for this month's durations, which change every month. It does not say which links can never drive at all.
The test
Each activity is two events, a start and a finish, and the finish is never before the start (a duration can shrink to zero, never below). Each link says one event comes at least its lag after another: finish to start for FS, start to start for SS, and so on. A link is redundant when some other path between the same two events carries at least as much lag. That holds for any durations, so deleting the link cannot change a date in this update or a later one. Where the lags being compared sit on different calendars, the link is marked "check" rather than sure, and stays in the downloaded file.
What it found
On the six public P6 files the project tests against:
| File | Open links | Redundant |
|---|---|---|
| CCA programme, 16,000 activities | 35,272 | 12,285 (34.8%) |
| Hotel | 7,586 | 587 (7.7%) |
| Expressway | 1,094 | 52 (4.8%) |
| Airport terminal | 84 | 4 (4.8%) |
| P6 analyzer example | 518 | 11 (2.1%) |
| Small sample | 41 | 0 |
In the CCA file they are spread out: 5,658 different predecessors. 5,779 are implied by a two-link chain, 3,313 by a three-link chain and the rest by longer ones. A few activities carry 181 redundant successor links each.
Checked by deleting them
The claim is checkable, so it was checked. Every link marked sure was deleted from a copy of each file at once, and both copies were rescheduled. Then every activity's early and late dates, total float and free float were compared. That was done with the file's own durations and again with five random sets of durations. Not one value moved: 15,849 activities compared six times on CCA after deleting 12,283 links. As a control, deleting the links that have another path but carry more lag than it did move dates: up to 6,476 activities on CCA, and the finish in one draw. So the comparison can see a change when there is one. Duplicates and A-to-C links planted over A-to-B-to-C chains were found 240 times out of 240.
The download is the original file less those TASKPRED rows. Every other line is kept exactly as exported, ready for P6's import. That import itself has not been tried yet: no P6 seat here.
Why bother
Redundant links make the relationship count look healthier to a DCMA or GAO reviewer than the network is. They also make a hand trace of the driving path slower. And when the activity that carried the real logic is deleted in a later update, the redundant link quietly becomes the only tie. A paid analytics product includes a redundant-logic metric. This one is free, runs in the tab and shows the chain behind each link.
The method and numbers are in the project's eval/redundant-logic-2026-11-23.md. There is also a guide: How to find redundant logic in a P6 schedule.