XER Schedule Check recomputes a Primavera P6 schedule in the browser: early and late dates, total and free float, then the checks built on them (DCMA, time impact analysis, the review of an update). The whole product depends on that engine giving the dates P6 gives. Until today it was scored on one kind of evidence: six real P6 exports, where P6's own dates are stored in the file. On those it matches 19,908 of 19,935 open activities on early finish, late finish and total float.
Real files have a weakness as a test, though. They are mostly ordinary finish-to-start logic. Rare cases show up once or not at all: the six files hold three start-to-finish links between them, and not one start-to-start link whose lag runs on a calendar other than the predecessor's.
A second oracle
A code search turned up a better source for the rare cases. cpp-cpm-engine (MIT) is another CPM engine, and its author publishes the tests they ran against P6: 338 small synthetic XER files, each built to isolate one behaviour, imported into Primavera P6 Professional 23.12.1 and scheduled once. P6's six values for every unfinished activity (early start and finish, late start and finish, total and free float) were read back from P6's database and committed next to the files, with a README for each set saying what it probes.
That is P6's own output on exactly the cases real files rarely contain: work set As Late As Possible while it is under way, start-to-finish links into started work, progress override against retained logic, mandatory constraints, and resource-dependent activities. So we scored our engine against all of it: node eval/p6-probes.mjs, half a second for the whole set.
The score
2,953 of 5,199 rows match P6 on all six values (2,929 before the fix below). That is far below the real-file figure, and it should be: these files were written to be hard. The breakdown matters more than the total:
| Rows | Match | |
|---|---|---|
| Files with no resource assignments | 1,775 | 74% |
| Files with resource assignments | 3,424 | 48% |
| Resource-dependent activities | 936 | 17% |
The biggest gap is clear. P6 schedules a resource-dependent activity on its resources' calendars. Our engine uses the activity's own calendar. On the six real files the two calendars are the same, so it never showed. A contractor whose crews work different hours from the activity calendar would see it. That is now the next item on the engine's list.
One rule fixed
The start-to-finish rows showed a smaller, exact fault. An As Late As Possible activity slides later by its free float. When it is under way and has a start-to-finish link into a successor that has also started, our engine treated the link as already satisfied and slid the work to the end of the project. P6 does not. It holds the work so that its remaining start plus whatever part of the lag is still unspent lands on the successor's finish. The lag counts from the predecessor's actual start, so time already worked uses it up. Under progress override the link holds only work that has not started yet.
With that rule, 24 more rows match and none that matched before stops. The six real files are unchanged. The rule was read off these probes, so those 24 rows are not an independent test of it. The other 2,929 were not used to fit anything.
Relationship dates on start-to-finish links
The run also closed a smaller item. P6 writes two dates on every link that no screen shows (TASKPRED aref and arls). The engine already reads them to find a lag that was edited after the last schedule run. Start-to-finish links were the one type not decoded. The three in the real files fit the same shapes as the other types: aref is the predecessor's early start plus the lag, less the successor's duration, and arls is the successor's late finish less the lag and the predecessor's duration. arls now agrees on 40,478 of 40,478 links between unstarted activities. Three links is a small sample. The formulas are the only ones that fit both unstarted links on both dates, so treat them as a reading, not a law.
The method, the tables and every row that still differs are in eval/p6-probes-2026-11-24.md. Anyone can rerun it: bash eval/corpus-fetch.sh DIR --probes, then node eval/p6-probes.mjs DIR/p6-probes.
XER Schedule Check is a free, open-source tool. Its results are estimates from the file you give it, not professional scheduling, legal or claims advice.