Rolling conformal calibration changed nothing for permit times, and why

We tried rolling and adaptive conformal calibration on Chicago and San Francisco permit review times. Coverage did not move to the fourth decimal.

Our permit-timing intervals are meant to cover 80% of 2024 permits but cover 86.7% in Chicago and 90.1% in San Francisco. The previous attempt (grouping by the chance a permit is same-day) failed, so we tried the obvious next lever: calibrate on a rolling window of already-known outcomes in 2024, with windows of 60, 120 and 365 days, all known outcomes, and Gibbs and Candès's adaptive conformal.

Result: coverage was identical to the static calibration in every column (Chicago 0.867, SF 0.901), and so was the interval width (68 and 63 days).

The reason is a point mass. Between 30% and 55% of permits are issued the day they are filed, and for those the conformal score is exactly 0. While that mass is above 20%, the 80th-percentile score is 0 whatever the window. In Chicago the same-day share fell from 52% in 2023 to 30% in 2024, a real shift, and still the shift in calibration stayed 0 days. The width comes from the model's own upper quantile, so the next experiment tunes that.

This is one test year and two cities; the log and code are in research/build-data/ (session 22). It was written with AI assistance and is not advice.