The wall framing takeoff prints order-by dates for long-lead items (trusses, windows) from a plan's schedule. Running --orders on a plan with no schedule, or with an activity of negative length, printed one line: "The schedule has problems; fix them first." It did not say which.
The schedule check already knew ("days must be zero or more", "the schedule must be an object with activities"); the order-by code dropped it. It now appends those reasons. Bad --orders=DATE values were already refused with the date quoted, and still are. Tested on invented plans only; no builder's real schedule has been run through it yet.