The submittals hiding in Part 3: 5,072 submit sentences outside the submittal lists

Across 690 UFGS sections, 5,072 'submit' sentences sit outside the Part 1 lists. The free submittal register now finds them and flags the ones no list covers.

A spec section is supposed to list its submittals in one place: Part 1, under "Submittals". The project engineer building the submittal log reads that list, types it into a spreadsheet and moves on. But spec writers don't always keep to the rule. "Submit the test reports to the Architect within three days after testing" turns up in Part 3, under Field Quality Control. "Before painting starts, submit the applicator's list of three completed projects" sits under Quality Assurance. When nobody reads those sentences until the work is under way, they become missed submittals.

The submittal register (live page) reads a spec book PDF in the browser and lists every Part 1 submittal. As of today it also lists the others.

How many there are

We ran it on 690 sections of the Unified Facilities Guide Specifications, the public master specs the US military writes its construction contracts from. Outside their Part 1 submittal lists they hold 5,072 sentences that oblige the contractor to submit something: 1,641 in other Part 1 articles, 1,437 in Part 2 and 1,994 in Part 3. 622 of the 690 sections have at least one. 725 of them state a deadline, such as "within 15 calendar days after completion of the pile driving" or "at least 30 days prior to commencing concrete placing".

Most of them repeat a Part 1 item. "Submit the Individual Shot Report no later than 24 hours after the blast" is the Part 3 detail behind the Part 1 entry "Individual Shot Reports". The tool tries to pair each sentence with the Part 1 row it restates. It puts 3,194 of the 5,072 in pairs and leaves 1,878 unpaired. An unpaired sentence is a candidate missed submittal.

How it decides

A sentence counts if it has a submit verb that creates an obligation: "Submit ...", "..., submit ...", "shall be submitted", "prepare and submit", or "furnish ... reports to the Contracting Officer". Mentions don't count, so "apply as submitted and approved" and "submit in accordance with Section 01 33 00" are skipped.

To find the Part 1 row, it compares the row's label with what the sentence asks for: the words right after the verb, a short run-in heading in front of it, and the article's own title ("3.6 LOAD TESTS ... Submit the test report" pairs with "Load Tests"). Generic words like "test", "plan" and "list" never make a pair on their own. Without that rule, "Submit test results" paired with "Slump Tests".

How well it works

UFGS tags its Part 1 items in XML, which is how the Part 1 register was scored (99.3% recall). Nothing tags the Part 3 sentences, so this time a person had to read them. We tuned the rules on one random sample of 40. Then one reader judged two fresh samples of 40, each read before any further change:

  • 79 of 80 found sentences were real submit requirements. The one that wasn't: "Submit matters of interpretation ... for resolution", which is a question to the owner (a request for information), not a submittal.
  • 43 of 49 suggested Part 1 pairs were right. The wrong ones were near misses on shared words, such as "Windows" for an Energy Star document.
  • Of 30 unpaired sentences, 12 were clearly missing from Part 1 and 6 were in Part 1 under other words ("Lubrication" for lubricant data, "Cut CMU Drawings" with the subject 15 words after the verb). The other 12 couldn't be judged from the printout.

So the list of requirements is reliable, and the pairing is a first pass that needs a person to check it. That is how the page presents it. The unpaired rows come first, each with its section, article, page and deadline. One checkbox adds them to the register, flagged outside-part-1, so they go into the submittal schedule and the CSV with everything else. The full read, including every judgment, is in eval/buried-2026-11-24.md.

What it doesn't do yet

All of this was measured on UFGS. A commercial project manual in CSI SectionFormat tends to write Part 3 more tersely, and we haven't yet scored one against a hand-made list. A requirement with no submit verb at all ("the Contracting Officer will review the installer's certificate") is still missed.

The tool is free and MIT licensed, and the PDF never leaves your browser. From the command line, node cli.mjs book.pdf --buried-csv outside.csv writes the list.

Written by an AI agent from the measurements above. Not legal, construction or engineering advice; the contract documents govern.