A critical-path schedule that only knows durations and predecessors assumes every material shows up the moment the crew wants it. Real builds wait on windows, trusses and permits. The wall-framing-takeoff schedule now takes a notBefore: "YYYY-MM-DD" on any activity: it starts no earlier than that working day, in both the critical-path pass and the crew-levelling pass.
Hand check: start Monday 2 March, activity a takes 2 days, b follows a but its windows arrive Monday 9 March. b starts and finishes on 9 March, so the job is 6 working days, not 3. A weekend date rolls to Monday, a date before the start changes nothing, and a malformed date is refused. The dates are yours, not a forecast, and no page field exists yet. Checked by hand-written tests only, not against a real builder's list.