Quality fix: our gate bid priced a 10 ft leaf the same as a 5 ft one

Our driveway gate bid asked for leaf height, printed it on the proposal, then priced nothing from it. Leaf cost and hang hours now scale with height.

A driveway gate that is twice as tall has about twice the pickets, panel and frame, and it is heavier to hang. The Automatic Driveway Gate Bid Calculator asked for the leaf height, checked it and printed it on the customer proposal ("16 ft opening × 6 ft leaf"). It then ignored it. A 10 ft leaf cost the same as a 5 ft one. The 2026-11-26 quality audit (audit file) rated this a high-severity defect: the proposal stated a scope the price did not cover.

What changed

The leaf rate ($ per lineal foot) and the hang hours per lineal foot now apply at a stated height, Leaf rates quoted at height. It is 5 ft by default and a shop can change it to match its supplier's quote. Leaf dollars and hang hours scale by leaf height ÷ that height. So a 6 ft leaf on 5 ft rates costs 1.2 times as much, and a 10 ft leaf twice as much.

Checked by hand on the default 12 ft single aluminum swing, which runs $85 per lineal foot and 0.35 hours per lineal foot:

  • at 5 ft: 12 × $85 = $1,020 of leaf and 4.2 hours to hang it;
  • at 10 ft: $2,040 and 8.4 hours;
  • the extra $1,020 plus 4.2 h × $55.44 loaded wage, with 16% overhead and a 28% margin on top, adds $2,018.48 to the price. The page in a browser went from $6,505.58 to $8,524.06, exactly that difference.

The two 5 ft presets did not move. The 6 ft ones did. The 16 ft dual steel swing on masonry now costs $15,278.85 instead of $14,716.71, and is priced at $21,220.62 instead of $20,439.88. The $4,500 special page and the pricing guide now show those figures. The guide's "almost half of that dual bid's cost is extra work" line now reads about 44%, which is the new share.

What is still not at the bar

Height now drives the leaf price, but not the operator. A heavier or taller leaf needs a bigger operator, and every gate style still gets one fixed-price operator per leaf. Other gaps the audit listed are also still open:

  • one photo-eye kit per job, while UL 325 needs entrapment protection for each zone;
  • a slide leaf priced at the opening width, with no cantilever tail;
  • a flat AC trench line.

They are listed under the tool's Limitations. A later audit round re-scores the tool; this fix does not raise its score.

All writing · More in Quality audits · All tools and research