The two dates P6 hides on every relationship, and the lag edits they give away

Every P6 XER stores aref and arls on each link. Decoded on 40,476 links: they carry the lag P6 used, so a lag changed after the last run reads back.

Open the TASKPRED table of almost any Primavera P6 .xer export and each relationship has two columns after the lag: aref and arls. No P6 screen shows them, the format notes we could find don't explain them, and XER Schedule Check ignored them until today. We worked them out on seven public P6 files (P6 5.0 to 20.12, plus P6 Web 17.12).

What they are

On a link between two activities that haven't started:

  • aref is the early start the link gives the successor: the predecessor's early finish plus the lag for FS, its early start plus the lag for SS, and for FF the early finish plus the lag, less the successor's duration.
  • arls is the late date the link gives the predecessor: the successor's late start less the lag for FS, its late finish less the lag for FF. For SS it is the successor's late start less the lag and less the predecessor's own duration, which is not what the name suggests.

arls matches on 40,476 of 40,476 links on the six files that store it. aref matches on 40,383. It's an hour or a few minutes off on 86 links in the P6 17.12 file and on 7 FF links in one other file. The P6 24.12 Web export we have doesn't write either column.

When the predecessor is finished, arls comes back from the successor's late date by only the part of the lag still unspent at the data date. That held on 1,894 of 1,894 such links. Our engine had already adopted the same rule a day earlier, working only from the late dates P6 keeps for finished activities, so P6's own link records confirm it independently.

Why a scheduler should care

P6 writes both dates in the same run as the activity dates. They record the lag P6 used at that run. If someone changes a lag and exports without rescheduling, the activity dates and the link dates still point to the old lag, and the old value can be read straight back.

The check we shipped yesterday could only catch a lag that had been lengthened until it broke the stored dates. A shortened lag breaks nothing, so it was invisible. Now the assessment's "Lags edited after the last schedule run" list includes changes in both directions, each with the lag P6 used. A link with no relationship dates, in a file where every other link has them, is listed as added after the run. To test it we planted 1,200 lag edits (10 days shorter to 20 days longer) and 1,200 added links in copies of the real files, without rescheduling. All 1,200 edits came back with the old lag exactly, all 1,200 added links were named, and nothing else was listed.

Two corrections it forced

Yesterday's post said a 608 h lag in the public CCA programme must have been edited after P6's last run, because the stored dates leave only 440 h for it. The link's arls says otherwise. It sits 200 h before the successor's late start, which is 608 h less the 408 h spent before the data date. P6's backward pass used 608 h. So the 168 h shortfall comes from P6's own forward pass, by a rule we haven't found yet. The tool now says that on the item.

The last five finished activities whose late dates we couldn't reproduce (a chain of pile caps behind CFNS103317C0) are closed. P6 stored a late date of 2011-10-26 17:36 on the root, which is an after-hours time on its calendar. On the same run it wrote an arls of 2011-10-10 09:36 on that activity's own link to the next pile cap, and that is the date our engine gives. No rule can reproduce a stored date that P6's own link record contradicts.

Method, tables and what wasn't checked: eval/relationship-dates-2026-11-20.md. The tool runs in your browser and doesn't upload the file. It gives screening metrics on your own schedule, not scheduling, contractual or legal advice.