XER Schedule Check reads a Primavera P6 .xer export in the browser and runs the DCMA 14-point assessment. Its recomputed dates match the ones P6 stored on 19,820 of 19,822 activities. As of today it also reads the cost.
What it computes
Many contracts ask for a cost-loaded schedule: each activity carries its share of the contract value, and the monthly pay application is tied to progress on it. The XER holds everything needed to check that:
- the budget, actual and remaining cost on every resource assignment (P6's
TASKRSRCtable), plus project expenses; - each activity's percent complete and how it is measured (physical, duration or units);
- the planned dates and the logic.
From those the new "Earned value and the S-curve" section gives planned value to the data date, earned value, actual cost, SPI, CPI, TCPI, three estimates at completion, and earned schedule. Earned schedule's SPI(t) is the schedule index that does not drift back to 1.0 at the end of a late job. You also get a monthly S-curve (planned, actual, then the forecast over the dates the engine recomputes from the logic), a breakdown by WBS, and a CSV of every activity. If no cost is loaded but labour hours are, it does the same in hours. The command line does the same with node cli.mjs schedule.xer --earned-value.
The checks that matter before paying
The numbers are only as good as the cost loading, so it also lists the activities behind each common fault:
- open work with no budget (it earns nothing, so the total misses it);
- cost booked on work that has not started;
- remaining cost left on finished work;
- progress claimed with nothing spent;
- value earned at more than 1.5 times what was spent (how a front-loaded claim shows up);
- overruns;
- remaining cost far below the budget still to be earned;
- actuals that equal earned value on nearly every activity.
A real file where the last check fires
We ran it on the public XER files the engine is tested against (eval note). One is a 16,000-activity hospital schedule exported from P6 6.0, with 632.6 million (EGP) of budget on its assignments. Its headline figures look excellent: 70% earned against 52% planned, SPI 1.34, CPI 1.000.
That CPI is exact, and that is the giveaway. On all 2,020 cost-loaded activities with actuals, actual cost equals budget times percent complete to within 0.1%. P6 can fill in actuals from progress ("auto compute actuals"), and this file was built that way. So the CPI says nothing about cost performance. A reviewer should ask for the cost ledger, and the tool now says so. The match also checks our side of the arithmetic: the percent complete the tool reads agrees with the one P6 applied on all 2,020 activities.
Two more things stand out in the same file. 12,352 open activities carry no cost at all. And the SPI of 1.34 sits beside a logic-driven forecast finish of June 2013. Earned schedule puts the finish around September 2012. That gap suggests the planned dates were moved along with the schedule, which P6 does for work that has not started. An XER export carries no timephased baseline, so planned value can only follow the dates in the file. The page says this next to the result.
A public expressway file shows a different fault. Its 21 budgeted activities are all unstarted, and they hold 111,528 (OMR) of budget but only 669 still to complete. Any estimate at completion built on that file comes out at 0.6% of the budget.
Limits
No public file carries P6's own earned value columns, so planned value is checked only for consistency: the curve ends on the budget, and the forecast ends on the estimate at completion, in every file. The 0/100, 50/50 and fixed-percent techniques are unit-tested but none of the public files uses them. As with everything on the page, the file stays in your browser.