XER Schedule Check already did two things with a job's monthly P6 updates. It ran a windows analysis, which shows how far the forecast finish moved in each period and whether progress or revisions moved it. And it read the earned value of one update. As of today it reads earned value across the whole series, one window at a time.
The problem with period SPI
The usual monthly figure is the schedule performance index (SPI): value earned divided by value planned, where planned value comes from the baseline. An XER has no timephased baseline. It has the planned dates, and P6 moves those for unstarted work whenever the schedule is run. Many schedulers re-plan as well. The "plan" that SPI measures against therefore tends to follow the work. On the public hospital file we checked this morning, SPI reads 1.34 while the logic forecasts a finish nine months later than earned schedule does.
So each window now carries a second measure. The previous update was the plan the contractor submitted for the period. For every open activity, the tool takes that update's recomputed remaining dates and works the activity for the hours up to the next data date. It then reads the percent complete the way P6 earns it: by duration, units or physical percent, or by the project's 0/100, 50/50 or custom technique. The total is what that update promised the period would earn. Earned divided by promised is 1.000 when the month went exactly as forecast. Moving planned dates cannot raise it.
Each window also gives:
- the period's planned value on the earliest update's planned dates, held as the baseline for the whole series, with SPI on that basis;
- what was spent, and the period CPI;
- the activities that earned less than promised (or more), that spent well past what they earned, whose budget changed (a revision, so both figures are read on the old budget and the change does not count as progress), whose earned value or actuals went down, and that were added or removed.
How we checked it
No public P6 file comes with its next month's update, so the check builds series from six public files. Update 2 is the file statused exactly as planned four weeks on. Update 3 is four more weeks with planted trouble: 40 extra hours on some activities worked in the window, and cost spent at 1.5 times the rate on others. To make this possible, the statusing code now posts cost and units with the work, at the planned rate.
| File | Window 1 (as planned) | Slips named | Overruns named | Other activities named |
|---|---|---|---|---|
| Hospital, P6 6.0, 2,020 cost-loaded activities | 1.000, nobody named | 20 of 20 | 20 of 20 | 0 |
| Demo, P6 24.12 | 1.000, nobody named | 20 of 20 | 16 of 16 | 0 |
| Hotel, P6 6.0 | nothing due | 1 of 1 | none eligible | 0 |
With 50 plants of each kind over five seeds, it named 435 of 435 slips and 250 of 250 overruns. On the hospital file, window 2 reads 0.973 to 0.993.
The first run named 18 of 20 slips on the hospital file. The ones it missed were real shortfalls but small. One activity was 99.6% done, its last 8 hours became 48, and it earned 0.07% of its budget where it was promised 0.4%. That fell under a threshold of 0.5% of the activity's budget. The threshold is now 1% of what the activity was promised in the window. The as-planned window still names nothing, because its rounding error is under a fifth of a currency unit on 50 million.
What it does not show
The promise and the generated series come from the same engine. So a 1.000 shows that statusing, the percent-complete reading and cost posting agree with each other, not that P6 would report the same number. The generator also never pushes a slipped activity's successors later. On a real update, work held up by a late predecessor also earns less than promised, and the tool names it too. The windows analysis beside it says whether that moved the finish. A real series of updates, and a real baseline export, are the next things to test against. Method and numbers are in ventures/xer-schedule-check/eval/evm-series-check-2026-11-20.md.
On the page, open all of a job's updates in the windows panel. If they are cost or hours loaded, the earned value table appears under the delay windows. From the command line: node cli.mjs --windows u1.xer u2.xer u3.xer --earned-value. Everything runs in your browser and nothing is uploaded. It is a review aid, not a cost audit or legal advice.