FOR FOUNDATION-REPAIR CONTRACTORS

Bid the access, the extra shaft, and the straps.

Price a foundation-repair job the way the trade actually loses money: helical or push piers, installed depth past the footage already in the pier price, interior brackets versus exterior access, an engineering stamp, carbon-fiber straps on a bowed wall, and plumbing under the slab. You get the bid, the price per pier, and the walk-away number below which the job loses money.

The house

Start from a common job, then replace every figure with your takeoff. Picking a method never overwrites a rate you already typed.

Your crew rates

A $42/h tech loaded at 34% is $56.28. Quoting the raw wage on a published per-pier special is how an interior-access house that looked fine turns into a week-long loss after the first cramped bracket.

Hand the customer a proposal

The price above is for you. This is the page you print or save as a PDF and give to the homeowner — your details, their details, the scope, the deposit split, and a line for them to sign. Your business details are saved on this device so you only type them once; the customer’s details are never saved.

Everything on the printed page is text you typed or a number this calculator worked out. It contains no warranty, lien, or cancellation wording — those depend on your jurisdiction and your contract, and this tool is not the place to invent them.

Your bid

$—
foundation-repair price
Piers / extra shaft
Access
Crew hours
Loaded labor
Materials + fees
Travel + equipment
Overhead
Total cost
Profit at this price
Price per pier
Effective hourly rate
Walk-away price

Where the hours go


Where the cost goes


Transparent arithmetic from your own inputs. Starting hours and material rates are common ballpark figures, not an industry standard, a settlement warranty, or an engineering specification — replace them with your own takeoff.

Common questions

Why can a competitor advertise a flat “price per pier”?

Usually because the quote is written around one specific job, and that job is a preset here: 8 exterior helical piers at 12 feet deep with easy access — the brochure job. It really does price low. What the per-pier number cannot see is interior access, depth past what is included, an engineering stamp, wall straps, and a plumbing reroute. Price your actual foundation beside the quote and the gap becomes a list of line items instead of an argument about who is honest.

Why does interior access cost more than exterior for the same pier count?

Because interior brackets mean working inside a finished or semi-finished basement — cramped clearance under joists, protecting floors and walls, and sometimes routing plumbing out of the way before a pier bracket can even go in. Exterior piers are set from open ground with equipment that cannot fit inside a house. Same pier, same depth, very different working conditions.

Why does depth past 10 feet add cost per pier instead of a flat per-pier rate?

Because each method’s per-pier price already includes a starting depth — 10 feet for both helical and push piers here — and every foot past that is additional drive time and additional pier segments, billed per foot rather than absorbed into the base price. A 16-foot pier in poor soil is not the same job as a 10-foot pier just because the brochure quoted “$X per pier.”

Is this the same as basement waterproofing or a concrete slab job?

No. This prices holding a settled or bowed foundation up and still — piers, extra shaft depth, interior access, engineering, and wall straps. It is distinct from basement waterproofing (a French drain, a sump pit, and a discharge line for water, not structure), new concrete pours, retaining walls (height and geogrid on a wall you are building), and crawl space encapsulation. A bowed wall with no settlement may only need straps or I-beams, priced here with zero piers.

Is my data uploaded anywhere?

No account and no network requests — the calculator runs entirely in your browser. A share link encodes only the inputs you choose into the address bar and is never sent to us; your bid is also saved in this browser’s local storage so it is still here next visit, and the optional usage counter records only which features were used and the day, never your pier count, wages, or prices.

What’s the difference between the bid price and the walk-away price?

The bid price already includes your target margin on top of labor, materials, and overhead. The walk-away price is the total cost underneath it — piers, extra depth, access, engineering, and wall straps — the point below which the job stops being profitable at all. Typing a price you are considering shows you the margin or the loss before you send it.

Want the margin, walk-away price and overrun headroom as well, or pricing a different trade? Price this job in the Bid Price Engine, one calculator for 121 trades.