Free CMMC POA&M template

A Plan of Action and Milestones (POA&M) workbook for a CMMC Level 2 self-assessment: one row per open item, each checked as you type against the rules of 32 CFR 170.21 (may this requirement sit on a POA&M, what it costs the score, is it due inside the 180-day close-out). No sign-up, no macros.

Download the POA&M template (.xlsx) Excel, Google Sheets, LibreOffice or Numbers.

What is in it

The rules it checks

Every requirement with its verdict is on which CMMC requirements can go on a POA&M. The Summary's score assumes every requirement not on the sheet is met; for the full score use the SPRS score calculator or the self-assessment spreadsheet, which shows which open requirements must be met first.

Writing an item an assessor can follow

Name the gap, not the requirement. "3.1.10 not met" says nothing; "Shop-floor CAD PCs (3) have no screen lock; office PCs lock after 15 minutes" says what is left. Give the remediation as the change you will make, the milestones as dated steps, and one person responsible. (That example is ours, not from a rule.) Each assessment objective under a requirement is listed on the Level 2 requirements page, and a requirement is met only when every one of them is.

Moving it into the workspace

Compliance Workspace keeps the POA&M next to the score and the SSP, shows for each item whether it may sit on a POA&M, and emails the shop's owner and admins 60 and 7 days before the POA&M close-out falls due. It reads this file: on the POA&M page choose Import spreadsheet, pick the workbook, check the preview (each row new or updated, with its rule) and apply. It reads Requirement, Weakness, Remediation plan, Milestones, Responsible, Scheduled completion, Status; a row without a weakness or a date is listed, not imported, and importing the same file again changes nothing. Recording Level 2 items needs the Level 2 plan (not on sale yet).

Common questions

Is there a free CMMC POA&M template?

Yes: this Excel workbook is free and needs no sign-up. One row per open item (requirement, weakness, remediation plan, milestones, responsible, scheduled completion, status), with each row checked against the 32 CFR 170.21 rules as you type and a Summary sheet with the points the open items cost and the 180-day close-out deadline.

What goes in a POA&M for NIST SP 800-171?

For each requirement not yet met: what exactly is missing (the weakness), how it will be fixed (the remediation plan), the steps and their dates (milestones), who is responsible and when it will be done. NIST SP 800-171 requirement 3.12.2 asks for plans of action that correct deficiencies; CMMC then limits which requirements may stay open on one for a conditional status.

How many items can a CMMC Level 2 POA&M have?

As many rows as you need, but for a Conditional Level 2 (Self) status only 1-point requirements may be open (46 qualify, plus 3.13.11 on partial credit) and the score with them open must stay at 88 or above, so at most 22 requirements can be open. Several rows may cover one requirement when it has several gaps.

Can I use the POA&M template for Level 1?

No. Level 1 allows no POA&M: all 15 requirements must be met (32 CFR 170.21). The template is for Level 2.

Does it work in Google Sheets and LibreOffice?

It is a plain .xlsx with ordinary formulas (IF, FIND, COUNTIFS, SUMIFS), so it opens in Excel, Google Sheets, LibreOffice and Numbers. Our tests recalculate it in LibreOffice.

General information, not legal advice. Your senior official decides what is met and affirms it in SPRS; the workbook submits nothing. Not affiliated with or endorsed by the DoD or the Cyber AB.