How to review the calendars in a P6 schedule

Every date in a Primavera P6 schedule is counted on a work calendar, and the calendars are the part of a schedule a reviewer reads least. P6 shows them one at a time in a dialog; the DCMA 14-point assessment never opens them. Yet a calendar can move the finish without a single logic or float fault: a holiday list that stops after the first year makes every later public holiday a working day, and an Hours per Day figure that does not match the calendar makes every duration shown in days wrong. The free tool here reads every calendar in an XER and lists what to fix.

Open the free schedule check (open the XER, then press Review the calendars)

Steps

  1. Export the schedule from P6 as XER (File, Export, Primavera PM XER). A P6 XML or Microsoft Project XML file can be opened too.
  2. Open it on the tool page.
  3. Under Calendar review, press Review the calendars. Faults come first, then things to check, then notes, each with the calendar and the activities on it. A table below lists every calendar: days a week, hours a day (and the stored figure), holidays, the last holiday, and how many activities use it.
  4. When a holiday list runs out, the what-if line says how far the forecast finish moves once the missing years get the calendar's own holidays back.
  5. Press Download findings (CSV) for one row per activity, to send with the review.

What it checks

A holiday on a day the week does not work (a Sunday on a Monday-to-Friday calendar) changes nothing and is not counted.

What it found on public schedules

Measured on six P6 files published on GitHub (the project's eval/calendar-review-2026-11-23.md names them). Three of the six had a holiday list that ran out before the work:

FileFindingWhat-if
Airport terminal buildingThe one calendar in use (66 activities) lists holidays to 24 December 2010; the work runs from May 2012 to February 2013Finish 2 working days later
Small sample fileHolidays to 25 December 2013; the work runs through 2021Finish 2 working days later
Hotel project"HBTF # 2 - all days" lists holidays to 2010 and carries 29 activities into 2013; "Standard 5 Day Workweek" works seven 9-hour days and says 8 hours a day; "HCRA - Global" (1,103 open activities) lists no holiday at allFinish 2 working days later
A 16,000-activity programme (CCA)Holidays listed to 2016, past the 2013 finish; Hours per Week says 40 on a 6-day calendar (48 hours)–
Expressway projectHolidays cover the work; 30 open critical activities on a 7-day calendar to ask about–
Example file from a P6 analyzerNothing found–

How it was tested

On the six public files, each year of holidays inside the open work on a used calendar was deleted in turn: the review named that calendar and that year 16 times out of 16. Deleting a year before the data date instead raised no new finding 33 times out of 33. Raising a calendar's Hours per Day by one hour was named 12 of 12 times, and setting it to the hours the days really hold raised nothing 12 of 12 times; renaming a calendar for the wrong number of days was named 12 of 12 times, and for the right number raised nothing 12 of 12 times. Where deleting a year made the finish early (7 cases, by 1 to 8 working days), the what-if put it back to within a day of the real holidays' finish in 4 cases; it missed by 3, 4 and 6 days where the year it copied from had a different holiday list from the year deleted.

Things to know

Questions

Why do holidays matter in a P6 schedule?

P6 counts every duration in working time on the activity's calendar. A holiday the calendar does not list is a working day, so work is scheduled through it and the forecast finish comes out earlier than the site can deliver. On a long project a calendar whose holiday list stops after the first year or two loses about a week and a half of non-working days for every later year.

How do I check whether a P6 calendar's holidays run out?

Export the XER and open it in the free check: under Calendar review it lists every calendar with its holidays per year and flags one whose list stops before the open work on it ends. In P6 itself you would open each calendar under Enterprise, Calendars and page through the months of every remaining year.

What is Hours per Day on a P6 calendar?

The figure P6 divides hours by to show a duration in days. P6 stores durations in hours; when the calendar works 9 hours a day but says 8, an activity shown as 10 days is 80 hours, which takes 8.9 of that calendar's days. The check compares the stored figure with the hours the calendar's working days actually hold.

Should every calendar have holidays?

Not always. A calendar used for curing, dewatering or other round-the-clock work may truly work every day. The check flags a calendar with no holidays only when it works fewer than seven days a week and carries open work, and lists critical work on seven-day calendars as something to ask about, not as a fault.

Is the file uploaded?

No. The schedule is read and analysed in your browser tab. There is no server, account or upload.