How to review a contractor's monthly P6 schedule update

Reviewing a schedule update means comparing it with the previous accepted update, not only checking it alone. Look for actual dates edited after they were reported, logic deleted on the critical path, durations shortened, new constraints, and then split the change in the forecast finish into the part progress caused and the part the contractor's revisions caused. The free tool does that comparison from the two XER files.

Open the free schedule check (open this month's XER and last month's together)

The questions to ask, in order

  1. Did the finish move, and why? A half-step run recomputes last month's schedule with only this month's progress applied. The difference between that and last month's finish is progress; the rest is revisions.
  2. Were reported actuals changed? An actual start or finish should never move once reported.
  3. Was logic deleted or changed on the critical path? Deleted links and changed relationship types are the usual way a slip disappears on paper.
  4. Were durations shortened on critical work? Ask for the crew or method change that makes the shorter duration real.
  5. Were constraints added? A new hard date holds an activity in place instead of letting logic drive it.
  6. What was forecast to start or finish this period and did not? These are the activities to discuss at the meeting.

A worked example

The tool's built-in example compares two updates of an invented office fit-out, 9 March and 6 April 2026 (press Load an example pair of updates on the tool page):

FindingDetailPriority
Forecast finish6 July → 27 July 2026, +15 working days: progress +8, revisions +7
Actual date edited after reportingSite survey actual finish moved from 4 to 5 MarchHigh
Relationship deleted on the critical pathFlooring → SignageHigh
Duration shortened on critical workPaint, 10 → 8 daysHigh
Constraint addedRough-in inspection fixed to start on 18 MayMedium
Relationship type changedDemolition level 1 → level 2, FS → SS +3 daysMedium
Duration lengthened, not startedProcure doors and hardware, 40 → 50 daysMedium
Activity deletedFinal clean, with both its linksLow
Due this period, not finishedSubmittal review, demolition levels 1 and 2Low

The useful reading: the job lost 8 days to slow progress, and the revisions made it 7 days worse rather than recovering any of it, while also shortening paint and deleting a critical link. Those revisions are what to ask the contractor to justify.

Across many updates

Open every update of the job at once and the tool runs a windows analysis: each consecutive pair compared the same way, the windows adding up to the whole movement, with the driving-path activities behind each window. The printable written review collects the findings and the corrections to request. On 36 update series built from six real P6 files with planted slips, lag changes and re-estimates, every split matched and every planted change was named in its window.

The comparison says what changed and how much it moved the dates. Whether a change is justified, and who carries the delay, is for the contract.

Questions

What is a half-step schedule analysis?

Last month's schedule recomputed with this month's progress applied but none of this month's logic, duration or constraint changes. The finish movement up to the half-step is due to progress; from the half-step to the new update it is due to revisions.

How are activities matched between two updates?

By activity ID, and relationships by predecessor, successor and type. Microsoft Project files are matched by Unique ID, so inserted rows do not break the comparison.

Can I review a Microsoft Project update the same way?

Yes. Save both updates as XML in Project and open them where the XER files go.

Does the tool decide whether a delay is excusable?

No. It measures what changed and how far it moved the finish. Entitlement depends on the contract and the facts.