New brands usually miss their launch date through waiting, not work: a second sample round, a factory closed for Lunar New Year, three weeks at sea. The clothing studio now has a production timeline planner that chains those waits.
Type the date stock must ship by and it returns the latest day you can start. Or type your start and it returns the earliest on-sale date. Stages are editable: tech pack, sample rounds, a pre-production sample, bulk cloth, production, inspection, freight and customs. Factory stages stop their clock during a closure window; freight and your own work do not. A delay allowance pads factory and freight stages, and you can download the schedule as a chart or CSV.
With the defaults (two sample rounds, sea freight, 30 production days, 15% delay) the chain is roughly seven months (209 days from a 15 January start), and that start loses 21 days to the closure window. Those defaults are my rough shape, not a quote, and the Lunar New Year dates are typed from memory: replace them with your factory's. No designer has run a real production through it yet.